Approximately 74% of Contracted Value Already in Execution, with Proposals Submitted for Approximately
Six New Projects Awarded in September; Formal Work Order Received for
Approximately 74% of that value relates to projects on which work has already commenced. The portfolio includes six new LPG engineering subcontracts awarded to
Contracted Engineering Portfolio and Expected Revenue Recognition
As of
Work has commenced on 56 of these contracts, which, together with related change orders, represent approximately AED 14.2 million (
As of
New Engineering Awards Expand Commercial Footprint
During
The projects encompass more than 215 residential units and an 80-unit commercial cloud kitchen facility, including:
- A five-story residential building with 85 apartments in Dubai South, valued at approximately AED 248,000 (
$67,500 ). - A seven-story residential building with 94 apartments in Dubai South, valued at approximately AED 240,000 (
$65,400 ). - An 80-kitchen commercial cloud kitchen development in Al Quoz Industrial Area 4, valued at approximately AED 210,000 (
$57,200 ). - A ten-story residential tower in Warsan 4th, valued at approximately AED 200,000 (
$54,500 ). - A five-story residential building with 36 apartments in Dubai South, valued at approximately AED 110,000 (
$30,000 ). - A two-story private villa with basement in
Dubai Hills , valued at approximately AED 57,000 ($15,500 ).
Under the subcontracts,
Several projects also include individual gas metering infrastructure, which may create opportunities for
Motor City Development Advances Into Execution
Separately,
The formal work order moves the Motor City project from award into execution, subject to the conditions described below. Under its terms, the work order constitutes a binding agreement between
The scope comprises the design, supply, installation, testing and commissioning of the development’s complete LPG system, including two 2,000 USG underground storage tanks, four 300 kg/hr vaporizers, central pressure regulation, gas detection systems, boiler connections and kitchen-level connections with individual gas meters. As announced on
The work order also establishes the payment schedule, under which
Repeat Developer Business and Additional Project Opportunities
Al Shola Gas's contracted engineering portfolio spans high-rise and mid-rise residential towers, mixed-use residential and commercial developments, private villas, and commercial kitchens for restaurants, cafés and cloud kitchen operators across
It includes three contracts on developments with a combined value of approximately AED 9.2 million (
Fourteen customers have awarded
Indicative completion dates for the contracts in the portfolio extend through the end of 2028. These dates are based on current project plans and are not fixed, and actual completion dates may vary depending on site conditions and access, material availability, and decisions and approvals from consultants, clients and authorities. Certain projects have experienced extended timelines, including two projects that commenced in 2021 and 2023, respectively, for which completion has been delayed due to delays in decisions and approvals on the clients’ side. Both projects remain active, and
In addition to its contracted engineering project portfolio,
These proposals remain subject to client evaluation and award, and there can be no assurance that any of them will result in contracts, or as to the timing, value or terms of any contracts that may be awarded.
2026 Revenue Outlook
Fusion Fuel continues to expect consolidated revenue of approximately €16 million to €18 million for the full year 2026, compared with approximately €14.4 million in 2025, representing anticipated year-over-year growth of approximately 11% to 25%. The approximately
“Importantly, our engineering installations may create opportunities to establish recurring LPG supply relationships as projects are completed, potentially extending the value of these contracts beyond the initial engineering work. With approximately
About Fusion Fuel Green PLC
Fusion Fuel Green PLC (Nasdaq: HTOO) is a diversified energy platform offering a comprehensive suite of energy supply, distribution, and engineering and advisory solutions through its operating businesses Al Shola Gas, Bright Hydrogen Solutions Ltd (“BrightHy Solutions”) and Biosteam Energy (Proprietary) Limited (“BioSteam Energy”). Al Shola Gas provides full-service industrial LPG solutions, including the design, supply, and maintenance of LPG systems, as well as the transport and distribution of LPG across commercial, industrial, and residential sectors. BrightHy Solutions, the Company’s hydrogen solutions platform, delivers engineering and advisory services enabling decarbonization across hard-to-abate industries. BioSteam Energy provides biomass-powered industrial steam solutions to clients. Through Royal Uranium Inc., the Company also holds a portfolio of uranium and natural gas royalty and other interests across Canada, Colombia and Argentina.
Forward-Looking Statements
This press release includes “forward-looking statements” within the meaning of Section 27A of the U.S. Securities Act of 1933, as amended, and Section 21E of the U.S. Securities Exchange Act of 1934, as amended. Forward-looking statements generally relate to future events or the Company’s future financial or operating performance and can be identified by words such as “may,” “will,” “believes,” “expects,” “anticipates,” “estimates,” “projects,” “intends,” “should,” “seeks,” “future,” “continue,” “plan,” “target,” “predict,” “potential,” or the negative of such terms, or other comparable terminology. Forward-looking statements in this press release include, but are not limited to, statements regarding: the anticipated project values of the six new LPG engineering subcontracts awarded in September 2026, individually and in the aggregate; the value and execution of the contracts and change orders in Al Shola Gas’s contracted engineering project portfolio, including the expected commencement of the 31 contracts on which work has not yet commenced and the indicative completion dates of contracts in the portfolio; the expected amount and timing of revenue recognition from the contracted engineering portfolio, including approximately $1.0 million in the fourth quarter of 2026, approximately $2.2 million in 2027 and approximately $1.0 million thereafter; the expected number of residential and commercial units to be served by the projects; the Motor City work order, including the satisfaction of its conditions, the execution of a formal subcontract agreement, the commencement of procurement and mobilization, and the receipt of payments and release of retentions under its payment schedule; the potential for gas metering infrastructure and completed installations to result in ongoing LPG supply and utility service relationships, and the potential annual utility revenue of approximately AED 2.95 million to AED 3.75 million ($805,000 to $1.02 million) from the Motor City, Studio City and other projects; the proposals submitted by Al Shola Gas for new projects with a combined value of approximately AED 50 million ($13.6 million) and the potential award of contracts in respect of those proposals; the Company’s 2026 revenue outlook and expected year-over-year revenue growth, and the expected contributions to that outlook from Al Shola Gas, BrightHy Solutions and BioSteam Energy; and the Company’s strategy of building a diversified energy platform with multiple sources of revenue and long-term cash flows. These forward-looking statements are based on current expectations and assumptions and are not guarantees of future performance, conditions, or results. They involve known and unknown risks, uncertainties, and other important factors, many of which are outside the Company’s control, that could cause actual results to differ materially from those expressed or implied, including, without limitation: the material uncertainty regarding the Company’s ability to continue as a going concern and its dependence on external financing; geopolitical instability or armed conflict in the Middle East, including disruptions to shipping through the Strait of Hormuz and the departure of customers from the region, that could disrupt Al Shola Gas’s operations, sales volumes, supply chain and costs in the UAE; the Company’s ability to support the expansion of the operations of Al Shola Gas; Al Shola Gas’s ability to execute awarded LPG engineering projects on time and within budget; the risk that developers, owners or general contractors delay, suspend, modify or cancel contracted or contemplated projects or change orders, thereby reducing, deferring or eliminating anticipated revenue; the risk that projects take longer to commence or complete than currently indicated, including as a result of site readiness, site conditions and access, material shortages or delays in decisions and approvals from consultants, clients or authorities, which could defer revenue recognition beyond the periods currently expected; the risk that clients fail to pay amounts invoiced when due or at all, including in light of 90-day payment terms, retentions and defects liability periods; the risk that the conditions to the Motor City work order, including pre-qualification approval and the provision of a performance guarantee, are not satisfied, or that a formal subcontract agreement is not executed on the anticipated terms; the risk that proposals submitted by Al Shola Gas do not result in contract awards, or result in awards on less favorable terms than anticipated; the risk that Al Shola Gas does not obtain LPG supply or utility operations contracts upon completion of engineering projects, or that any such contracts generate less revenue than estimated; the risk that the Company does not achieve its 2026 revenue outlook, including as a result of lower sales volumes at Al Shola Gas, the failure of Al Shola Gas’s historical fourth-quarter seasonal pattern to recur, or delays in revenue recognition on BrightHy Solutions’ projects or lower than expected revenue from BioSteam Energy; fluctuations in demand for LPG engineering and distribution services; regulatory approvals and compliance requirements affecting LPG distribution and engineering services in the UAE; volatility in energy markets and LPG and other commodity prices; Al Shola Gas’s ability to obtain sufficient financing, including any performance guarantees, to support operations and growth initiatives; risks related to foreign exchange, including fluctuations in the U.S. dollar against the euro and the potential for adjustment of the AED/USD exchange rate that could reduce the U.S. dollar value of the projects; and the risks and uncertainties described in Exhibit 99.2 to the Report on Form 6-K/A furnished by the Company with the U.S. Securities and Exchange Commission (the “SEC”) on July 29, 2026, in the Company’s Annual Report on Form 20-F for the fiscal year ended December 31, 2025, as amended by Amendment No. 1 filed with the SEC on October 6, 2026, and in the Company’s other filings with the SEC. All forward-looking statements in this press release are qualified in their entirety by the cautionary statements above. The Company does not undertake any obligation to publicly update any forward-looking statement to reflect events or circumstances that may arise after the date hereof, except as required by law.
Investor Relations Contact
ir@fusion-fuel.eu
www.fusion-fuel.eu
Source: Fusion Fuel Green PLC