HIGHLIGHTS FOR Q2 FISCAL 2027
As disclosed on
- Production results: Produced approximately 0.9 million ounces of silver, 1,371 ounces of gold, or approximately 1.0 million ounces of silver equivalent1 during the quarter;
- Revenue of
$72.1 million , a decrease of 13% over the three months endedSeptember 30, 2025 ("Q2 Fiscal 2026") due to lower production, which was partially offset by an 82% higher average realized silver price of$61.83 per ounce and a 32% higher gold price of$3,955 per ounce;
- Cash cost per ounce of silver (net of by-product credits) was
$2.14 , and all-in sustaining cost per ounce of silver1 (net of by-product credits) was$24.13 , both affected by the safety system improvements which caused less metals to be produced and sold;
- Adjusted earnings before interest, income tax, depreciation and amortization ("EBITDA") attributable to equity shareholders of
$37.7 million , or$0.17 per share, compared to$38.3 million or$0.18 per share in Q2 Fiscal 2026;
- Net income attributable to equity shareholders of
$5.3 million , or$0.02 per share;
- Adjusted earnings attributable to equity shareholders of
$18.4 million , or$0.08 per share, after excluding the non-cash or one-time items, compared to$22.6 million or$0.10 per share in Q2 Fiscal 2026;
- Cash flow from operating activities of
$62.7 million , up$23.5 million , compared to$39.2 million in Q2 Fiscal 2026, including the$43.9 million draw-down from Wheaton inJuly 2026 ;
Mine Development & Construction : spent and capitalized$26.6 million on exploration, development, equipment and facilities at the China operations,$14.6 million at theEcuador operations mainly for the development and construction of the El Domo mine, and$9.2 million for Chaarat ZAAV mine construction and drilling activities;
- Free cash flow generated of
$4.7 million , down$6.7 million , compared to$11.4 million in Q2 Fiscal 2026, mainly due to the Company's planned investments to build new mines;
- Strong treasury position: ended the period with cash and cash equivalents and short-term investments of
$383.7 million , a decrease of$3.4 million from the previous quarter, after$50.5 million of capital expenditures on mine construction. In addition, the portfolio of equity investments with a total market value of$428.0 million increased by$124.4 million from the previous quarter; and
- Subsequent to
30 September, 2026 , completed an initial draw-down ofRMB750 million (approximatelyUS$112 million ) under theRMB1.5 billion syndicated term loan facilities for general corporate purposes and to support the Company's global working capital requirements.
_____________________ |
1 Non-GAAP measures, please refer to section 13 for reconciliation. |
CONSOLIDATED FINANCIAL AND OPERATING RESULTS
Three months ended | Six months ended | |||||
2026 | 2025 | Changes | 2026 | 2025 | Changes | |
Financial Results (in thousands of $, except per share) | ||||||
Revenue | $ 72,097 | $ 83,330 | (13) % | $ 210,762 | $ 164,664 | 28 % |
Mine operating earnings | 39,883 | 40,858 | (2) % | 124,636 | 76,681 | 63 % |
Net Income (loss)* | 5,315 | (11,516) | 146 % | 64,690 | 6,610 | 879 % |
Per share - basic | 0.02 | (0.05) | 146 % | 0.29 | 0.03 | 875 % |
Per share - Diluted | 0.02 | (0.05) | 146 % | 0.27 | 0.03 | 809 % |
Adjusted earnings* | 18,354 | 22,551 | (19) % | 72,280 | 43,599 | 66 % |
Per share - basic | 0.08 | 0.10 | (20) % | 0.33 | 0.20 | 63 % |
Per share - Diluted | 0.07 | 0.10 | (30) % | 0.28 | 0.20 | 41 % |
EBITDA* | 28,107 | 5,567 | 405 % | 112,580 | 39,337 | 186 % |
Per share | 0.13 | 0.03 | 399 % | 0.51 | 0.18 | 182 % |
Adjusted EBITDA* | 37,705 | 38,312 | (2) % | 114,988 | 73,290 | 57 % |
Per share | 0.17 | 0.18 | (3) % | 0.52 | 0.34 | 55 % |
Cash flow from operating activities | 62,684 | 39,180 | 60 % | 124,366 | 87,461 | 42 % |
Sustaining capital expenditures | 5,415 | 11,952 | (55) % | 16,091 | 22,789 | (29) % |
Growth capital expenditures | 43,434 | 15,858 | 174 % | 63,301 | 30,788 | 106 % |
Free cash flow | 4,655 | 11,370 | (59) % | 33,259 | 33,884 | (2) % |
Basic weighted average shares outstanding | 221,210,023 | 218,585,686 | 1 % | 221,174,549 | 218,290,025 | 1 % |
Metals sold | ||||||
Silver (million ounces) | 0.9 | 1.7 | (47) % | 2.4 | 3.5 | (31) % |
Gold (ounces) | 1,574 | 2,033 | (23) % | 4,028 | 3,984 | 1 % |
Lead (million pounds) | 7.5 | 14.8 | (49) % | 21.2 | 30.0 | (29) % |
Zinc (million pounds) | 1.1 | 5.7 | (81) % | 5.3 | 10.9 | (51) % |
Average Selling Price, Net of Value Added Tax and Smelter Charges | ||||||
Silver ($/ounce) | 61.83 | 33.89 | 82 % | 66.61 | 31.60 | 111 % |
Gold ($/ounce) | 3,955 | 2,986 | 32 % | 3,938 | 2,932 | 34 % |
Lead ($/pound) | 0.97 | 0.91 | 7 % | 0.98 | 0.94 | 4 % |
Zinc ($/pound) | 1.75 | 0.98 | 79 % | 1.42 | 0.97 | 46 % |
Cost Data per ounce of silver, net of by-product credits ($) | ||||||
Cash cost | 2.14 | (0.002) | 107,041 % | 1.63 | 0.58 | 181 % |
All-in sustaining cost | 24.13 | 13.94 | 73 % | 20.49 | 13.70 | 50 % |
Financial Position (in thousands of $) as at |
|
|
|
| ||
Cash and cash equivalents and short-term investments | $ 383,744 | $ 387,107 | (1) % | $ 383,744 | $ 422,335 | (9) % |
Working capital | 289,132 | 293,236 | (1) % | 289,132 | 319,461 | (9) % |
*Attributable to equity holders | ||||||
INDIVIDUAL MINE OPERATING PERFORMANCE
(i)
Cash cost per tonne of ore was
AISC per tonne was
Three months ended | Six months ended | |||||||
September | June | March | December | September | September | September | ||
Ore processed (tonnes) | ||||||||
Silver-lead ore | 188,061 | 290,064 | 279,627 | 299,217 | 235,168 | 478,125 | 488,126 | |
Gold ore | 25,259 | 33,152 | 32,050 | 29,208 | 29,834 | 58,411 | 60,231 | |
213,320 | 323,216 | 311,677 | 328,425 | 265,002 | 536,536 | 548,357 | ||
Average head grades for silver-lead ore | ||||||||
Silver (grams/tonne) | 157 | 160 | 161 | 190 | 207 | 159 | 213 | |
Lead (%) | 2.0 | 2.1 | 2.2 | 2.3 | 2.6 | 2.0 | 2.7 | |
Zinc (%) | 0.3 | 0.4 | 0.4 | 0.4 | 0.4 | 0.3 | 0.5 | |
Average head grades for gold-ore | ||||||||
Gold (grams/tonne) | 1.1 | 1.2 | 1.1 | 1.2 | 1.4 | 1.2 | 1.4 | |
Silver (grams/tonne) | 46 | 48 | 54 | 57 | 81 | 47 | 66 | |
Lead (%) | 0.6 | 0.9 | 0.9 | 1.1 | 0.9 | 0.8 | 0.8 | |
Recovery rates | ||||||||
Silver (%) | 94.1 | 94.8 | 95.0 | 95.3 | 94.8 | 94.5 | 94.7 | |
Gold (%)* | 92.9 | 90.5 | 90.8 | 92.8 | 94.2 | 91.5 | 93.8 | |
Lead (%) | 90.4 | 92.4 | 93.2 | 93.6 | 93.5 | 91.6 | 93.8 | |
Zinc (%) | 57.7 | 65.2 | 63.9 | 63.0 | 65.8 | 62.7 | 64.9 | |
Cash Costs | ||||||||
Cash cost ($/tonne) | 96.76 | 87.05 | 78.27 | 75.80 | 82.89 | 91.00 | 83.03 | |
AISC ($/tonne) | 143.87 | 130.25 | 134.23 | 134.06 | 139.22 | 135.76 | 134.41 | |
Cash cost, net of by-product credits ($/ounce of silver) | 2.73 | 2.45 | (1.03) | (1.22) | 0.97 | 2.56 | 1.12 | |
AISC, net of by-product credits ($/ounce of silver) | 16.11 | 13.94 | 13.09 | 11.32 | 11.75 | 14.76 | 10.88 | |
Metal Production | ||||||||
Silver (million ounces) | 0.9 | 1.4 | 1.7 | 1.7 | 1.5 | 2.3 | 3.2 | |
Gold (ounces) | 1,371 | 2,536 | 2,492 | 2,096 | 2,085 | 3,907 | 4,135 | |
Silver equivalent (million ounces) | 1.0 | 1.6 | 1.5 | 1.9 | 1.7 | 2.6 | 3.6 | |
Lead (million pounds) | 7.6 | 12.4 | 12.9 | 14.7 | 12.9 | 20.1 | 27.5 | |
Zinc (million pounds) | 0.7 | 1.6 | 1.4 | 1.9 | 1.4 | 2.3 | 3.3 | |
*Gold recovery only refers to the recovery rate for gold ore processed. | ||||||||
Capacity Expansion and Technical Transformation
To expand the scale of mining production and advance deep resource extraction, the Company is implementing expansion and technical transformation projects across all four mining rights of the
Reserve | Mining License Update | Production Safety Permit | ||||||
Reserve | Mining | 3-in-1 | Updated | Environmental | Safety facility | Underground | Production | |
SGX | v | v | v | Submitted | v | In progress | In progress | |
TLP-LM | v | v | v | Submitted | v | In progress | In progress | |
HPG | v | v | v | v | v | In progress | In progress | |
DCG | v | v | v | Submitted | In progress | In progress | In progress | |
*3-in-1 report includes the Mineral Resource Mining Plan (including the Development and Utilization Plan) and the Mine Area Ecological Restoration Plan. |
Safety Compliance Process Status
Major safety improvement works at the
Meanwhile, the Company is obtaining environmental, safety and land permits for the construction of multiple waste rock storage facilities, to accommodate the additional waste rock produced from extensive tunneling activities, given the aggregate plant cannot process and sell all waste rock generated. Please refer to the details below:
Waste-Dumps | Status | Design volume ('000 m3) | Progress | |
SGX | ZG | Operating | 483 | Reaching full capacity |
HZG | Planned | 10,072 | Application submitted | |
HPG | QZ | Operating | 1,080 | In use |
TLP-LM | 960m | Operating | 640 | In use |
JDG | Planned | 12,632 | Geotechnical study | |
LDG | Planned | 207 | Design Approved | |
SCG | Planned | 3,479 | Design Approved | |
DCG | No. 1 | Planned | 638 | Application submitted |
No. 2 | Planned | 485 | Application submitted |
(ii)
In Q2 Fiscal 2027, the GC mine processed 477 tonnes of stockpiled ore and produced approximately 0.01 million ounces of silver, 0.2 million pounds of lead and 0.1 million pounds of zinc, representing production decreases of 91% (silver), 87% (lead) and 97% (zinc) compared to Q2 Fiscal 2026.
Mining activities at the
Three months ended | Six months ended | |||||||
Ore Production (tonne) | 477 | 63,237 | 48,840 | 87,095 | 76,249 | 63,714 | 151,118 | |
Head grades | ||||||||
Silver (grams/tonne) | 51 | 51 | 52 | 52 | 64 | 56 | 66 | |
Lead (%) | 1.1 | 0.8 | 0.9 | 1.0 | 0.9 | 0.9 | 0.8 | |
Zinc (%) | 1.9 | 2.3 | 2.6 | 2.9 | 2.8 | 2.4 | 2.6 | |
Recovery rates | ||||||||
Silver (%) | 83.6 | 84.0 | 86.3 | 85.9 | 85.8 | 85.5 | 85.6 | |
Lead (%) | 94.8 | 92.3 | 93.5 | 89.1 | 89.0 | 93.3 | 89.5 | |
Zinc (%) | 87.8 | 90.6 | 90.6 | 92.7 | 91.1 | 90.5 | 90.6 | |
Cash Costs | ||||||||
Cash cost ($/tonne) | N/M* | 74.59 | 71.12 | 53.37 | 58.20 | 79.29 | 60.38 | |
AISC ($/tonne) | N/M* | 115.17 | 109.68 | 68.53 | 82.63 | 129.89 | 91.23 | |
Cash cost, net of by-product credits ($/ounce of silver) | N/M* | (16.90) | (19.93) | (29.05) | (11.44) | (18.94) | (5.98) | |
AISC, net of by-product credits ($/ounce of silver) | N/M* | 15.00 | 10.22 | (15.66) | 4.71 | 14.69 | 12.57 | |
Metal Production | ||||||||
Silver (million ounces) | 0.01 | 0.1 | 0.1 | 0.1 | 0.1 | 0.1 | 0.3 | |
Lead (million pounds) | 0.2 | 1.0 | 1.1 | 1.7 | 1.3 | 1.2 | 2.4 | |
Zinc (million pounds) | 0.1 | 2.9 | 2.5 | 5.1 | 4.2 | 3.0 | 7.6 | |
*Not meaningful. Mining activities at the | ||||||||
GC Mine Production to Remain Suspended
Mining activities have been suspended since late
The Company has engaged
Most technical personnel at GC have been reassigned to operations at the
Silvercorp has initiated a process to evaluate strategic alternatives to maximize the value and optimize the re-development of the
CAPITAL EXPENDITURES AND DEVELOPMENT FOR GROWTH
Total capital expenditures in Q2 Fiscal 2027 were
- China Operations:
Capital Expenditures | Capitalized Expenditures | |||||||
Ramps and Development Tunneling | Exploration Tunneling | Exploration Drilling | Plant and Equipment | Total | ||||
(Metres) | ($ Thousand) | (Metres) | ($ Thousand) | (Metres) | ($ Thousand) | ($ Thousand) | ($ Thousand) | |
Q2 Fiscal 2027 | ||||||||
11,640 | $ 11,115 | 10,139 | $ 5,087 | 8,578 | $ 333 | $ 8,204 | $ 24,739 | |
60 | 111 | 121 | 114 | -- | -- | 475 | 700 | |
Kuanping | 1,507 | 824 | 462 | 440 | 4,759 | 152 | 88 | 1,206 |
Subtotal | 13,207 | 12,050 | 10,722 | 5,641 | 13,337 | 485 | 8,767 | 26,645 |
Q2 Fiscal 2026 | ||||||||
8,879 | $ 6,122 | 12,639 | $ 5,271 | 34,767 | $ 977 | $ 822 | $ 13,191 | |
1,323 | 605 | 1,799 | 673 | 4,509 | 98 | 36 | 1,412 | |
Kuanping | 831 | 736 | 613 | 221 | -- | -- | 220 | 1,178 |
Subtotal | 11,033 | 7,463 | 15,051 | 6,165 | 39,276 | 1,075 | 1,078 | 15,781 |
i)
Capitalized expenditures for underground ramps, tunnels and drilling amounted to
ii)
Total capitalized expenditures amounted to
iii)
In Q2 Fiscal 2027, capital expenditures for Kuanping mine construction totaled
- Ecuador Operations:
Capital Expenditures ($ Thousand) | Package #1* | Package #2* | Package #3* | Packages #4&5* | Construction and Permanent Camps | Direct costs sub-total | Owner's Cost | Total |
Q2 Fiscal 2027 | ||||||||
5,181 | 1,553 | 1,206 | 731 | 1,166 | 9,836 | 4,342 | 14,178 | |
Q2 Fiscal 2026 | ||||||||
6,944 | -- | -- | 671 | 194 | 7,809 | 2,397 | 10,206 | |
*Package #1 - Site preparation/Roads/Channels/TSF/SWD Package #2 - Open Pit Mining and Stripping Package #3 - Packages #4&5 - Site Infrastructure (bypass roads, power line, standby diesel generators, water treatment plant) | ||||||||
i)
In Q2 Fiscal 2027, capital expenditures for El Domo totaled
Civil works at the process plant are progressing well as this site is protected by the Northeast Water Channel. The foundations for the plant buildings and main equipment were completed, waiting for installation. The pre-fabricated structural steel for the Process Plant has been shipped from the factory, and the first batch of major long lead-time equipment has also arrived in the
Construction of a power substation at the El Domo site and the external power line to connect to the power grid has also commenced, while 10 gen-sets of 17 MW capacity are ready to be shipped to site as an independent power supply, as required by
Open-pit pre-stripping has also been impacted by heavy rainfall with insufficient non-acid generating ("NAG") rock supplied for the construction of the TSF "
On
ii)
The Company increased its ownership of the
In Q2 Fiscal 2027, total expenditures incurred and capitalized were
The Company has continued to advance the Free, Prior and Informed Consultation ("FPIC") and Citizen Participation Process ("PPC") required to obtain the small-scale mining environmental license. On
- Kyrgyzstan Operations:
Kyrgyzstan Operations ($ Thousand) | Phase 1 Tulkubash | Phase 2 Kyzyltash | Total | |||||||||||
Mining | Heap Leach System | Commis-sioning | G&A | Contin- gency | Sub-total | Drilling & Studies | ||||||||
Mine Auxiliary Facilities | Heap Leach | Crusher | ADR Plant | Process Plant Auxiliary Facilities | ||||||||||
Three months ended | ||||||||||||||
Chaarat ZAAV | 751 | -- | 34 | 1,593 | -- | -- | -- | 2 | -- | 1,951 | -- | 4,331 | 4,912 | 9,243 |
i)
The Tulkubash project advanced rapidly with
ii)
A 50,000 m drilling program, including both in-fill and step-out, has completed 25,414 m or
CONFERENCE CALL DETAILS
A conference call to discuss these results will be held on
International/Local Toll: 437-900-0527
Conference ID: 88986
Participants should dial-in 10 – 15 minutes prior to the start time. A replay of the conference call and transcript will be available on the Company's website at www.silvercorpmetals.com.
Mr.
About Silvercorp
Silvercorp is a Canadian mining company producing silver, gold, lead, and zinc with a long history of profitability and growth potential. The Company's strategy is to create shareholder value by 1) focusing on generating free cash flow from long life mines; 2) organic growth through extensive drilling for discovery; 3) ongoing merger and acquisition efforts to unlock value; and 4) long term commitment to responsible mining and ESG. For more information, please visit our website at www.silvercorpmetals.com.
For further information
Silvercorp Metals Inc.
Lon Shaver
President
Phone: (604) 669-9397
Toll Free 1(888) 224-1881
Email: investor@silvercorp.ca
Website: www.silvercorpmetals.com
ALTERNATIVE PERFORMANCE (NON-GAAP) MEASURES
This news release should be read in conjunction with the Company's Management Discussion & Analysis ("MD&A"), the unaudited consolidated condensed interim financial statements and related notes contains therein for the three months ended September 30, 2026, which have been posted on SEDAR+ under the Company's profile at www.sedarplus.ca and on EDGAR at www.sec.gov, and are also available on the Company's website at www.silvercorpmetals.com under the Investor section. This news release refers to various alternative performance (non-IFRS) measures, such as adjusted earnings and adjusted earnings per share, EBITDA and EBITDA per share, adjusted EBITDA and adjusted EBITDA per share, free cash flow, cash cost and all-in sustaining cost per ounce of silver, net of by-product credits, cash cost and AISC per tonne of ore processed, silver equivalent, and working capital. The tonnage of ore production refers to wet tonne, containing approximately 2% to 3% moisture. These measures are widely used in the mining industry as a benchmark for performance, but do not have standardized meanings under IFRS as an indicator of performance and may differ from methods used by other companies with similar description. The detailed description and reconciliation of these alternative performance (non-GAAP) measures have been incorporated by reference and can be found under section 13 – Alternative Performance (Non-GAAP) Measures in the MD&A for the three months ended September 30, 2026 filed on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov and which is incorporated by reference here in.
CAUTIONARY DISCLAIMER - FORWARD-LOOKING STATEMENTS
This news release includes "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within the meaning of applicable securities laws (collectively, "forward-looking information") relating to, among other things, mineral resource and mineral reserve estimates at the Company's material properties; estimated production from the Company's mines in the Ying Mining District and the GC Mine; the suspension of mining at the GC Mine; the timing of completion and approval of the updated mine design and safety facilities design; construction of safety facilities; the receipt of a new safety production permit, completion of related construction and resumption of production at the GC Mine, and the timing therefor; the completion and effects of the safety works at the Ying Mining District; the expected impact of the GC Mine suspension; the Company's review of strategic alternatives relating to the GC Mine; timing of receipt of permits and regulatory approvals; availability of funds from production to finance the Company's operations; access to and availability of funding for future construction, use of proceeds from any financing and development of the Company's properties; and estimated El Domo and Kuanping mine construction progress. By its very nature, forward-looking information involves known and unknown risks, uncertainties and other factors that may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Forward-looking information may in some cases be identified by words such as "will", "anticipates", "expects", "intends" and similar expressions suggesting future events or future performance.
We caution that all forward-looking information is inherently subject to change and uncertainty and that actual results may differ materially from those expressed or implied by the forward-looking information. A number of risks, uncertainties and other factors, including but not limited to: fluctuating commodity prices; recent market events and condition; estimation of mineral resources, mineral reserves and mineralization and metal recovery; interpretations and assumptions of mineral resource and mineral reserve estimates; exploration and development programs; climate change; economic factors affecting the Company; timing and estimated amount of capital and operating expenditures and economic returns of future production; integration of future acquisitions into existing operations; permits and licences for mining and exploration in China; title to properties; non-controlling interest shareholders; acquisition of commercially mineable mineral rights; financing; competition; operations and political conditions; regulatory environment in China; regulatory environment and political climate in Bolivia, Ecuador and Kyrgyzstan; integration and operations of Adventus; government safety inspections and suspensions; the suspension of the GC Mine and uncertainty around production restart; environmental risks; natural disasters; dependence on management and key personnel; foreign exchange rate fluctuations; insurance; risks and hazards of mining operations; conflicts of interest; internal control over financial reporting as per the requirements of the Sarbanes-Oxley Act; outcome of current or future litigation or regulatory actions; bringing actions and enforcing judgments under U.S. securities laws; cyber-security risks; public health crises; the Company's investment in New Pacific Metals Corp. and Auro Metals Inc.; and the other uncertainties, risks and other factors described in the Company's Annual Information Form and filed with the U.S. Securities and Exchange Commission as part of the Company's Form 40-F and other filings with Canadian and U.S. regulators on www.sedarplus.ca and www.sec.gov, could cause actual results and events to differ materially from those expressed or implied in the forward-looking information or could cause our current objectives, strategies and intentions to change. Accordingly, we warn investors to exercise caution when considering statements containing forward-looking information. We cannot guarantee that any forward-looking information will materialize and you are cautioned not to place undue reliance on this forward-looking information. Any forward-looking information contained in this news release represents expectations as of the date of this news release and is subject to change after such date. However, we are under no obligation (and we expressly disclaim any such obligation) to update or alter any statements containing forward-looking information, the factors or assumptions underlying them, whether as a result of added information, future events or otherwise, except as required by law. All of the forward-looking information in this news release is qualified by the cautionary statements herein.
A comprehensive discussion of other risks that impact Silvercorp can also be found in its public reports and filings under the Company's profile on SEDAR+ at www.sedarplus.ca, on EDGAR at www.sec.gov, and on the Company's website at www.silvercorp.ca.
Cautionary Note to United States Investors Concerning Estimates of Reserves and Resources
Reserve and resource estimates included in this news release have been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy, and Petroleum Definition Standards on Mineral Resources and Mineral Reserves. NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for public disclosure by a Canadian company of scientific and technical information concerning mineral projects. Unless otherwise indicated, all mineral reserve and mineral resource estimates contained in the technical disclosure have been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum Definition Standards on Mineral Resources and Reserves. Canadian standards, including NI 43-101, differ significantly from the requirements of the Securities and Exchange Commission, and mineral reserve and resource information included in this news release may not be comparable to similar information disclosed by U.S. companies.
View original content to download multimedia:https://www.prnewswire.com/news-releases/silvercorp-reports-adjusted-net-income-of-18-4-million-0-08-per-share-and-cash-flow-from-operating-activities-of-62-7-million-for-q2-fiscal-2027--302931394.html