Hut 8 Corp. Q3 F2026 Earnings Call Transcript
AI Conference Call Analysis
Sign in or subscribe to read.Mark Eidelman
Investor Relations
Good morning, and welcome to HUD-8's third quarter 2026 financial results conference call. Joining us today are our CEO, Asher Genoot, and our CFO, Sean Glennan. Following the presentation, we will open the line for questions. This event is being recorded in a transcript we made available on our website. In addition to the press release issued earlier today, a full quarterly report on Form 10-Q is available at HUD-AID.com, on our EDGAR profile at sec.gov, and on our CDERplus profile at cderplus.ca. Unless otherwise indicated, all figures discussed today are in U.S. dollars. Certain statements made during this call may constitute forward-looking statements within the meaning of applicable securities laws. These statements reflect current expectations and are subject to risks and uncertainties that could cause actual results to differ materially. Certain key risks are detailed in our Form 10-K for the year ended December 31st, 2025 and our other continuous disclosure documents. Except as required by law, we assume no obligation to update or revise any forward-looking statements. During the call, management may reference non-GAAP measures such as adjusted EBITDA. We believe these metrics, alongside GAAP results, provide valuable insight into our performance. Reconciliations of GAAP and non-GAAP results are included in the tables accompanying today's press release, available on our website. I'll now turn the call over to Asher.
Asher Genoot
Chief Executive Officer
Thank you, Mark, and good morning, everyone. Over the past year, we have contracted 949 megawatts of IT capacity under long-term AI data center leases with or backstop by investment-grade companies, representing approximately $27 billion of contracted revenue. Realizing that revenue and the returns that we underwrote against it requires three disciplines. First, the quality of the power and the contracts that we originate. Second, our execution in delivering what we have contracted. And third, our rigor in financing. Those are the three principles we outlined for investors in May. And my remarks this morning will address each in turn, origination, delivery, and financing. Sean will then review the results in detail. Before I turn to the quarter, I want to step back to the premise behind all three measures, because it explains why we sequence them in that order. AI is delivered as software. but it is produced by physical infrastructure, power, land, transmission, buildings, cooling, equipment, and the people who operate them. The next generation of compute will be constrained not only by chips, but also by that infrastructure. And of everything that infrastructure requires, power is a scarce input. That is why we are a power first company. The input that is hardest to secure is the one we secure first. We developed the discipline of building within that constraint in Bitcoin mining, which required us to operate power-dense compute to manage cooling and uptime and to procure and build quickly. AI is the largest opportunity we have yet encountered to apply that same discipline. Procuring power, however, only earns the right to build. Converting it into contracted revenue depends on how efficiently we build, and that is the second part of what defines HUD-8. I'm convinced that the infrastructure behind AI can be built better than it is being built today, faster, at a lower cost, and without compromising on quality. Many of today's data centers resemble NASA rocket programs, remarkable engineering, but complex, expensive, and slow to deliver. and frankly, this is the mold that RubberBed and BeaconPoint Phase 1 follow. This approach makes sense when the build-out is small, but will not work at the multi-gigawatt scale at which I expect HUD-8 to build. Our future builds therefore start with a different question, what each system must do and how it should be designed and delivered. We are rethinking builds from there with the aim of improving speed and cost efficiency, with quality held as a constant We have done this before. Vega, a Bitcoin mining facility we designed in-house with direct liquid-to-chip cooling, was built in under six months. We believe we can apply the same approach to our future builds, and we believe that our ability to rethink builds to be more cost-efficient and shorten delivery times while maintaining quality through innovation will differentiate HUD-8 with customers. With that as context, I will turn to the quarter, beginning with origination, which is where the power is secured. For investors, origination is the measure of whether we control sufficient power on terms that support attractive commercialization opportunities to continue converting our pipeline into leases comparable to those at Riverbend and Beacon Point. We originate through three channels, and we advanced each throughout the quarter. The first is front-of-the-meter greenfield development. Our pipeline now includes more than 6.4 gigawatts under diligence and under exclusivity. Capacity under exclusivity, the stage at which we have secured a defined path to ownership, increased by approximately 1.3 gigawatts during the quarter as existing projects advanced and new projects were originated. PL alone does not answer the question investors ask most often about that pipeline, which is how geographically diversified is it? This quarter, we are providing a breakdown of our front-of-the-meter greenfield pipeline by geography. The largest shares are in MISTO, PJM, and SERC. Less than 5% is in ERCOT. That distribution reduces our regulatory and price exposure in any single market. It does not, however, diminish the value of our existing Texas interconnects, which we believe have become more valuable as ERCOT's revived interconnection process has lengthened the time required to secure approvals for new interconnections. The second channel is behind the meter development, which allows us to unlock power and accelerate delivery where traditional grid timelines are constrained and which builds on years of experience developing and operating such projects. We are actively evaluating opportunities across our campuses. Consistent with our disciplined approach, however, we do not include that capacity in our reported development pipeline until a contract is executed. Riverbend illustrates that point. Beyond the current phase under construction, we continue to develop the site. We have cleared 184 acres for campus expansion and are advancing site preparation now so that construction can begin promptly once the next phase is commercialized and approvals are secured. The third channel is corporate development, in which we acquire powered assets. Our approach here is the one that produced BeaconPoint, where we secured the power, underwrote the site on Bitcoin mining as its initial use, and applied our Greenfield development capabilities to advance the site and convert it into an AI data center campus. This quarter, corporate development yielded another opportunity as we entered into a definitive agreement to acquire from affiliates of Poland two energized data center sites in West Texas, with up to 230 megawatts of utility capacity upon full energization, subject to final power approvals and infrastructure development. Second, delivery. Each lease we sign obligates us to deliver capacity by a contracted date, and the lease revenue begins only on delivery. For investors, delivery is therefore the measure of whether the capacity we have contracted begins generating rent on the dates to which we committed, and it is our central operating priority. Construction at Riverbend and Beacon Point Phase 1 remains on track to meet our delivery targets, and both projects are funded entirely at the project level. At Riverbend, More than 1,200 people are on site. Structural steel, roof decking, and building foundations are complete on all four data halls. The slab at data hall one is also complete, and the remaining three data halls will follow through year end. Roofing and precast wall panels have also been installed at data hall one, with the remaining halls expected to follow through by mid-December, reducing the exposure of interior electrical and mechanical work to weather-related disruption. We expect to energize the substation in phases, and equipment installation has begun in Data Hall 1, starting with Vertiv IT Power Skids and SmartRun Overhead Modulars. At Deakin Point Phase 1, ground improvements are approximately 95% complete. Building foundation work and underground utilities installation are underway. The steel erection is scheduled to begin this month. We have also begun foundation work for the substation. For Beacon Point Phase 2, civil design and surveying are underway. We also amended the Beacon Point Phase 2 lease with our customer, extending its term from 15 to 17 years. The extension serves both parties. For our customer, it secures capacity over a longer horizon, which reflects the durability of demand for power. For HUD-8, it adds two years of contracted revenue for lenders to underwrite. which should help offset potentially higher financing costs as we look to finance Phase 2. The amendment applies to Phase 2 only. Phase 1 remains on its existing terms and the construction and financing framework for the campus is unchanged. Delivery also depends on the support of the communities in which we build, which we treat as a precondition of development rather than as an obstacle to be managed. Riverbend demonstrates what is required to convert power first approach into a real project. Power, transmission, land, construction, partners, and community alignment must come together in the right order. That is what more than 300 investors, analysts, media, government stakeholders, and community members saw when they visited Riverbend last month. I joined Governor Jeff Landry of Louisiana and leaders from Anthropic, Entergy Louisiana, Broadcom, Birdham and Jacobs to discuss the future of American AI infrastructure and those discussions reached one conclusion. Demand, supply, delivery and policy are inseparable. Sound technical plans matter, but durable projects are built transparently in partnerships with the people who live and work nearby. In Louisiana, that partnership has taken specific form. We are investing approximately $16 million in a new water well and nearly eight miles of water infrastructure, none of which will be used to cool the data center and which will be transferred to the parish at no cost to local taxpayers and can serve more than 4,000 households and 200 local employers. We also made a $10 million payment in lieu of taxes bringing tax revenue to West Feliciana Parish one year earlier than it otherwise would have arrived, supporting local government, schools, and law enforcement, including $7,000 stipends for school employees in each of the next two school years and payments of up to $8,000 for eligible sheriff's office personnel. At Beacon Point in Texas, the commitments differ in form, but not in principle. We are funding the electrical upgrades that our campus requires so that those costs are not shifted to residential rate payers, and the campus uses closed-loop cooling design to minimize local water demand. Across both phases, we anticipate approximately 1,900 construction jobs and more than 200 permanent positions supported by partnerships with local educators and workforce organizations. We make these commitments because we believe a successful project must create lasting value Not only for our customers and shareholders, but also for the communities that host it. We uphold this philosophy by investing in the infrastructure, workforce, and partnerships that allow our projects and the communities around them to grow together.
Various Analysts
Analyst Acknowledgements / Transcription Artifact
Third, financing.
Asher Genoot
Chief Executive Officer
For investors, how we finance our projects is a measure of our ability to limit risk to the parent balance sheet and avoid dilution for existing shareholders. Two of the main questions we've been asked as a supporter is directly to that point. How are our current builds progressing and might we need to issue additional equity to support them? The answers are straightforward. We remain on schedule and we do not expect to issue additional equity to support Riverbend or Beacon Point. Riverbend and BeaconPoint Phase 1 are funded through completion with investment-grade project bonds of $3.25 billion for Riverbend and $4.25 billion for BeaconPoint Phase 1, each non-recourse to Hut 8. We were able to raise investment-grade financing for both projects through a comprehensive approach to risk mitigation. Operating in Bitcoin mining taught us how quickly markets can change. and inflation and interest rate expansion are present realities. We cannot control the market, but we can control what we secure in advance and how we contract. We work from first principles to understand what every component must do and what it should cost. At Riverbend and Beacon Point Phase 1, all long lead equipment has been ordered and all major contracts have been signed, locking in the largest components of costs ahead of further market movements. Risk mitigation extends beyond procurement. Our principal equipment and construction partners, Vertiv and Jacobs, are investment-grade counterparties. Comprehensive insurance coverage is in place at both sites, providing an additional layer of protection against covered losses that could affect the projects and in turn bondholders. And the triple net lease structure makes tenants responsible for operating expenses, taxes, and insurance, which further supports this framework. A measure of the strength of our financings is that both bonds have traded well in the secondary market. That matters because capital has become scarcer across today's markets, and we believe scarcity produces a flight to quality. Investor interest in future issuance remains strong. In a tighter market, we believe contract quality and the flexibility to access multiple debt capital markets gives us a competitive advantage. and as we evaluate financing for future projects, we will start from first principles with a clean slate, tweaking the lowest cost of capital and the highest free cash flow yield on a risk-adjusted basis. How we originate, how we deliver and how we finance also answers the most direct question investors ask. What will drive the stock? We believe execution is how we create long-term shareholder value. We do not manage the daily share price We manage the delivery of rubber band and beacon point into the conversion of our pipeline into contractive projects because those are the outcomes within our control. The same long-term focus governs how we allocate capital. Every decision is evaluated against a single criteria, whether it equates long-term shareholder value. Alongside investing in growth, that criteria allows us to opportunistically create shareholder value by repurchasing our shares when we believed the stock trade at a discount to intrinsic value. We have acted on that conviction since last quarter by repurchasing approximately 3.3 million shares for approximately $250 million, funded with about 3,100 Bitcoin from our balance sheet. The repurchase met our criterion because we believe our shares do not fully reflect the value of the revenue we have contracted and the power capacity that we control. Funding it with Bitcoin rather than with cash preserved liquidity and continue the reduction in parent level Bitcoin exposure that we described in February.
Sean Glennan
Chief Financial Officer
Underneath those measures is a simple proposition.
Asher Genoot
Chief Executive Officer
We are builders and we believe the AI era will reward the companies that bring power and compute online faster, more cost efficiently, and without compromising on quality. That is the company we are building. The revenue we have contracted will be realized the way it was secured, by starting with power, underwriting carefully, preserving flexibility, and delivering. Those principles govern the three measures I have described, and those measures are how we expect to be judged in the quarters of 10. We believe they are the foundation of an enduring generational business at the intersection of energy and technology. With that, I will turn the call over to Sean.
Sean Glennan
Chief Financial Officer
Thanks, Asher. The financial story this quarter has four main components. First, the operating platform remained resilient. Revenue was $71.1 million for the third quarter, compared with $83.5 million in the prior year period, while adjusted EBITDA increased to $33 million from $30.5 million. That result reflects the contribution from additional operating capacity and a disciplined approach to cost. Despite the sale of the Far North portfolio in February, a decline in average revenue per Bitcoin mined, and the planned runoff of businesses that are no longer central to our strategy. Second, the GAAP result was heavily affected by the fair value remeasurement of digital assets. We reported net income of $189.5 million, of which $131.1 million was attributable to Huddy. That result included a $413.8 million gain on digital assets. Reflecting the increase in the price of Bitcoin during the quarter. To help investors assess operating performance alongside these price movements, we supplement our gap results with adjusted EBITDA, a non-gap measure, and our segment results. Adjusted EBITDA should be considered together with and not a substitute for gap net income. Third, we continue to maintain cost discipline even as we scale the company. While we are making major investments to scale them to the company we want to become, we are doing so judiciously. The rigor around spend decisions has not changed since I started two years ago, when the company was in more of a startup phase. Compared with the prior year period, G&A, excluding stock-based compensation, our megawatt of development pipeline has declined, even as our development pipeline has nearly doubled. And last, but arguably most important, the balance sheet and capital position of the company remains strong. We have fully funded two construction-stage projects, Compute. Compute revenue was $68.4 million in the third quarter, compared with $70 million in the prior year period. Headline revenue was broadly stable because the decline in average revenue per Bitcoin mined was largely offset by an increase in Bitcoin mined, reflecting additional operating capacity at Vega and the re-energization of Drumheller. That result demonstrates the enterprise's ability to scale revenue across a range of external environments. compute cost of revenue increased to $28 million from $22 million, primarily because we were operating more capacity and incurring the associated electricity costs. The increase tracked the increase in production, not a deterioration in operating efficiency. The important point is that we are producing more Bitcoin from a larger operating footprint, again, demonstrating the ability to scale in a cost-conscious manner. AI cloud revenue also increased during the quarter as new customer contracts came online. That growth was partially offset by the sale of the traditional cloud business in August. Power. Power revenue is $1.3 million in the third quarter, compared with $8.4 million in the prior year period. The decline was primarily the result of the sale of the Far North portfolio in February. It is therefore a portfolio composition effect, not a deterioration in the remaining hour business, which generates revenue primarily from managed services contracts. Digital Infrastructure Digital infrastructure revenue was $1.4 million in the third quarter, compared with $5.1 million in the prior year period. The decline primarily reflects the termination of the bigger co-location agreement after American Bitcoin exercised its purchase option for the miners at that site, together with the customer churn in the legacy CPU infrastructure business. The current digital infrastructure results do not yet reflect the contracted lease revenue from Riverbend and Beacon Point. That revenue begins when the relevant capacity is delivered. The financial model is therefore moving through an intentional transition. The legacy revenue base is no longer the main growth driver, while the larger contracted infrastructure revenues remain tied to delivery milestones. Adjusted EBITDA was $33 million, compared with $30.5 million in the prior year period. We use this measure to evaluate operating performance after excluding the effect of fair value re-measurement of digital assets and other one-time or non-cash items. As always, adjusted EBITDA should be considered alongside GAAP results, not in place of them. Reported general and administrative expense was $99.6 million, compared with $25.9 million in the prior year period. Approximately $64.7 million of this quarter's GNA was stock-based compensation, including the effect of one-time long-term incentive awards. The quarter also included professional fees and approximately $6.2 million of incremental salaries and benefits as we added people to support energy origination, corporate development, and other growth functions. Excluding non-cash costs, the cash GNA was $34.8 million. which compares with $24.8 million last quarter and $19.5 million from a year ago. We do not view all of that spending as recurring corporate overhead. A meaningful portion reflects the cost of building the organization required to originate, finance, construct, and operate multiple large campuses in parallel. At the same time, the cash component is real and we are holding those investments to a clear standard. They must support one or more of the following outcomes over time. More high-quality power origination, faster project conversion, a lower cost of capital, better execution, or stronger operating leverage. The balance sheet requires an important distinction between corporate liquidity and project-restricted capital. At September 30, 2026, we had approximately $156.9 million of cash, $3.6 billion of restricted cash and cash equivalents, and $2.8 billion of restricted short-term investments. The restricted balances are principally crocheted from the Riverbend and Beacon Point financings held in project accounts for construction, debt service reserves, and other specified project purposes. They are not excess corporate cash. Hud8 also has about 1,361 unencumbered Bitcoin on the balance sheet as of November 1st. The company had approximately $7.6 billion of consolidated loans, notes payable, and other financial liabilities. Approximately $7.5 billion of that amount relates to the Riverbend and Beacon Point project finance inks. Those obligations sit at project subsidiaries, are secured by the applicable project assets and accounts, and are non-recourse to HUD-AID's parent company. Each project is designed to serve as its own debt from its own contracted lease cash flows. The quarter also included $105.5 million of interest expense and $61.8 million of interest income. The interest expense reflects the construction period carry on the Riverbend and Beacon Point financings. The interest income was generated by investing unused project proceeds in restricted short-term investments to partially offset that carry. We accepted that construction period interest cost because the projects are fully funded upfront. The parent-level financing architecture is separate and quite simple. In September, we added a $1.07 billion senior secured revolving credit facility to support corporate liquidity, development need, and letters of credit. No borrowings were outstanding under that facility as of September 30th, 2026. The facility gives us committed capacity without requiring us to draw debt before we need it. We also simplified the parent capital structure during the year. The CO2 note converted into equity. The Coinbase facility was refinanced with the Bitcoin-collateralized FalconX term loan at a lower coupon, and the remaining TGRC-secured promissory note was repaid in October. We are also planning to retire the FalconX term loan ahead of its maturity in April 2027. The objective is straightforward. Maintain parent-level flexibility, match financing to the asset that generates the cash flow, and avoid using corporate equity where project-level capital is available on better terms. During the quarter, we sold approximately 954 Bitcoin for $74.8 million and used those proceeds to repurchase 953,802 shares for $74.7 million. Subsequent to quarter end, we've repurchased additional shares under the $250 million program. In total, we repurchased approximately 3.3 million shares for approximately $250 million, funded with approximately 3,100 Bitcoin. Those repurchases converted a portion of the strategic Bitcoin reserve into equity at a price we believe did not reflect the contracted revenue and power capacity controlled by the company. They also continued the reduction of parent-level Bitcoin exposure that we have described previously. Our board has also authorized an increase in our share repurchase program from $250 million to $1 billion. We view this as a long-term program that gives us the flexibility to act when opportunities arise over the coming years. We will be patient and judicious in how we deploy it, so that we maintain liquidity to run our business and pursue opportunistic growth. Stepping back, investors should evaluate HUD-8 through three layers. The first is the solid footing of the current operating platform, where the quarter demonstrated increased Bitcoin production, a growing AI cloud contribution, and adjusted EVTA above the prior year period despite lower revenue. The second is the contracted infrastructure platform, where Riverbend and BeaconPoint are being funded and delivered through project-level structures tied to long-duration customer commitments. The third is the development platform, where we are advancing power opportunities while preserving flexibility on the application, the customer and the financing structure. Our financial objective is not to maximize headline growth at any cost, Before we transition to Q&A, let me address what is likely to be the first question.
Asher Genoot
Chief Executive Officer
The outcome of the governor's race in Texas and its implications for Beacon Point. We respect the election outcome and support the governor-elect Hinojosa's call for legislative guardrails. We also expect Texas to remain a business-friendly state and recognize the benefits that data centers bring to local communities through tax revenue and jobs. As we discussed earlier in the context of Beacon Point and Riverbend, our focus is on building responsibly with local communities in mind. A commitment that we believe aligns with Governor Hinojosa's objectives. We do not believe the results change the outlook for Beacon Point, which as a late stage project is well positioned. For Beacon Point Phase 1, our baseload designation remains subject to Governor Abbott's audits. We believe we are well placed in that process and anticipate an unconditional classification on December 17th. which will provide a clear path to energizing the full gigawatt at beacon point with 700 megawatts expected in the first quarter of 2027. With that, happy to take questions.
Conference Call Operator
Operator
At this time, in order to ask a question, press star then the number one on your telephone keypad. If you would like to withdraw your question, press star one again. Thank you. Your first question comes from the line of Ryan Gravette with UBS. Please go ahead.
Ryan Gravette
Analyst, UBS
Great, thank you. Asher, I did want to just follow up on your closing remarks there, just given the election outcome last night. Anything you can share in terms of various other permits required for both Phase 1 and Phase 2 at Beacon Point? And then maybe one for Sean. Anything you can share in terms of expected timing for project financing at phase two of Beacon Point and if the election outcome changes that timeline at all. Thank you.
Asher Genoot
Chief Executive Officer
Thanks for the question, Ryan. In regards to the build, we're primarily focused on the December 17th timeline. When we think about TCEQ and any permits in regards to the diesel generators, there are paths to be able to design around that and use the BEST system as an alternative backup source. And so those are kind of the primary focuses for us as we continue to progress and develop the project. Sean, I'll pass it to you.
Sean Glennan
Chief Financial Officer
Yeah, so the sort of timing that's right in front of us doesn't really change. We expect to hear back from the audit results on December 10th and then have those be finalized on December 17th. Those remove largely the sort of remaining impediments ahead of us to get going on the financing for Beacon Point 2. There are a lot of different ways that we can see to finance that. Obviously, we've addressed and tapped the investment grade bond market, and we think there are a number of other avenues around that that exist too. So we feel really confident about the ability to get that done. In our minds, the path is the same as it was before, and so we look forward to executing on that.
Various Analysts
Analyst Acknowledgements / Transcription Artifact
Got it. Thanks, guys.
Conference Call Operator
Operator
Your next question comes from the line of Eric Lubcha with Wells Fargo. Please go ahead.
Eric Luebchow
Analyst, Wells Fargo
Great. Thanks for the question. I'm curious, given everything going on in terms of higher labor costs, more upfront investment in the sites in terms of utility deposits, what are you seeing in terms of your build costs, not just for Beacon Point and Riverbend, but as you look at your power pipeline today, are you seeing build costs move into the Loaded Midteens on a dollar per critical load megawatt basis. And do you think that you have enough pricing power to kind of maintain or even improve your development yields as you build out the next phase of your pipeline? Thank you.
Asher Genoot
Chief Executive Officer
Appreciate the question, Eric. I'll answer that in three parts. Part one is origination. Part two is the development in EPC. And part three is the commercialization and lease rates. for part one in regards to origination, you're right, a lot of utilities now ask for more upfront collateral kayak payments to make sure that the infrastructure upgrades or energy supply that's committed to doesn't affect rate payers. And we've been supportive of that since day one, and that's the same structure that we've had at Riverbend and Beacon Point in paying for those kayak upgrades and any collateral that's necessary. and so as we continue to develop our approach remains similar which is we don't put large development capital at risk in the pursuit of commercialization. We stay disciplined in the origination process which makes it difficult, more difficult to originate but we found opportunities where we are able to do so, able to bring customers along for the process with us and be able to continue to develop the sites that have that we have conviction in. As our balance sheet continues to grow, we obviously will be working on more sites across our pipeline. As you see this quarter, we had another 1300 megawatts of sites go from energy under diligence to energy under exclusivity, which means we're diving deeper into those sites. We're spending more resources in developing those projects. And so we really think about it as a percentage of overall development capital as we continue to scale that we can increase to develop those sites. But we are spending, call it, hundreds of thousands or single-digit millions up front in these developments and not tens of millions or hundreds of millions of dollars. Really when the collateral requirements come, we're deeply engaged with the end user during those moments in time. In regards to EPC, everyone has heard labor rates have gone up, you have supply chain rates that have changed, and as we've continued to build over the larger of a decade here, the focus has been how can we control our destiny? Well, we can't control our macro conditions of overall capital markets, of overall cost of labor, equipment, et cetera. What we can control is how do we design the infrastructure to be able to drive additional efficiency to try to offset those changes and those increases that you had mentioned. And so if we can ruthlessly focus on learning from the build that we have today, designing from first principles, driving efficiencies in the design, which ultimately drive efficiencies in the supply chain and the equipment we need to purchase, which ultimately drives efficiencies in the construction and the amount of hours we need to construct a data center. Those are things that are in our control and that we have conviction and confidence that we continue to build towards. So that is our offset against these macro conditions that you mentioned and I chatted about earlier in my prepared remarks on how We want to build a scalable, repeatable model like the Raptor photos of the Tesla engine that I'm sure many people have seen during iteration one, two, and three of SpaceX versus kind of a bespoke build every single time that is expensive and costly and time intensive. And then the last one is in terms of lease rates. We've always approached the market from a perspective of signing leases that we believe are fair and kind of middle of the fairway market from a lease rate perspective. And our shareholders and our investors have been happy with the structuring and the returns on those deals. So the way that we think about it is if market costs on average across the industry go up, therefore, lease rates would move in proportionally with that because many folks work on a more yield on cost basis. And so we'll charge market based rents. Meanwhile, focus on driving ruthless efficiency within our execution EPC SAC to construct and hold costs on construction, which could in turn actually increase the yield on the projects that we're developing if revenues go up and we're able to maintain costs.
Various Analysts
Analyst Acknowledgements / Transcription Artifact
Thanks, Asher.
Conference Call Operator
Operator
Your next question comes from the line of Brian Baratian with Roth Capital Partners. Please go ahead.
Brian Baratian
Analyst, Roth Capital Partners
Hey, guys. Thanks for taking my questions. I have two. One is, you know, as we, you know, in the face of the election and looking to what I think is one of the most interesting things is riverbend expansion where you have a gig of IT capacity to expand there. How can we think about what the structure looks like with regard to ultimate counterparty? I know at the Riverbend site day, the head of Computed Anthropic was there, and it all seemed very positive. But would we expect to see, similar to your other leases, the same level of investment-grade equity support that was both across Riverbend and Beacon Point with different tenants? Or how are you thinking about structuring that?
Sean Glennan
Chief Financial Officer
Is there a second one?
Brian Baratian
Analyst, Roth Capital Partners
Or do you want me to answer the first one? Oh yeah, you can start with the first and then I'll do the second. It's separate.
Asher Genoot
Chief Executive Officer
Okay, sounds great. We're very excited for Riverbend. We have been for quite some time and have shared some with the market. There's been a good amount of work that has been done. We believe that there's actually more than a gigawatt of gas available on the pipelines that run through the property and have been working towards being able to actualize and realize the continued expansion of that campus. When we look at the end commercialization, obviously I can't speak to any deals that we haven't announced yet, but we continue to stay focused on the credit quality of our end-off take relative to the investment in CapEx and the capital we ultimately need to raise. We're pretty open. I was on a call with a non-AI lab, non-investment-grade counterparty yesterday, someone we admire a lot in the business that they've created, We were open. We said, look, it's very hard for us to tell our shareholders and our board to go and build infrastructure for folks that don't have the credit that supports the ability to bring on the financing that we brought on historically to be able to build and execute these projects at scale. And so I don't want to speak to any deals that aren't announced yet, Brian, but overall, maintaining balance sheet, maintaining credit profiles, our cash flows, continues to be a core focus of the business and ones that shareholders have asked us for as well.
Brian Baratian
Analyst, Roth Capital Partners
Awesome, thanks. And the next one is, as we think about the existing footprint of opportunities that you have, I know American Bitcoin is running north of 400 megawatts of capacity. I guess in the face of the election that happened today, How are you, or if you can provide any color on, thinking about potential brownfield opportunities as it relates to the existing footprint there, or is the focus just going to continue being on greenfield development?
Asher Genoot
Chief Executive Officer
When you look at our pipeline that we've announced, the development pipeline is almost 8 gigawatts with a total of about 8.6 gigawatts. in terms of our overall pipeline overview. That is one out of four buckets of the ability to commercialize and realize additional TCV. That bucket is our greenfield origination bucket. The second one we have is the behind the meter generation bucket, which I chatted about more so in your first question in Riverbend and other sites that we have. The third one is M&A through our corporate development team. There continues to be very interesting opportunities. and growing opportunities in a world where capital becomes more constrained and flows to proven operators. And then the fourth is brownfield opportunities as well on existing campuses. So we continue to look at all four of those, continue to originate across all four, which gives us a strong conviction that outside of the publicly disclosed pipeline, we have three other pipelines with dedicated teams looking at opportunities there. All right, thanks. Thank you. Appreciate it.
Conference Call Operator
Operator
Your next question comes from the line of George Sutton with Craig Hallam. Please go ahead.
George Sutton
Analyst, Craig-Hallum
Thank you. Asher, I found it interesting that your energy capacity under diligence came down, but your capacity under exclusivity went up. Can you just give us a sense of that just sounds like a more focused way to go to market? Is that the right way to read that?
Asher Genoot
Chief Executive Officer
That's exactly right. The way to think about our pipeline is a funnel. you start top of funnel more wide. And as you get deeper and deeper in, more resources get allocated, more time gets committed to sites, we close in the aperture. And so at every stage, the requirements get higher and higher as we continue developing those sites. And so we have kind of clear guardrails before projects pass from one stage to another, and we dedicate additional resources to it. So you see a transition from capacity and diligence to exclusivity through quarter over quarter.
George Sutton
Analyst, Craig-Hallum
Just one quick question on, you know, when we watched you build Vega, that was just simply a better mousetrap at the time, really shortening delivery times and lowering costs. When you look at the application of these kinds of principles to the AI development, can you just give us a sense of how significant can those deltas be in your view and maybe looking out a couple of years?
Asher Genoot
Chief Executive Officer
Very significant. We've done more than a couple of tours in recent months at Vega, sharing our design philosophy and abilities. It's actually pretty interesting because before we started building Riverbend and Beacon Point, we had self-engineered, designed a lot of our own infrastructure and GC'd all of it. So Vega, if you go to that campus, you not only see the first principles of design mythology, but you see the components in which we designed and contract manufacturers, everything from the pipe skids to the PDU, the switch gears and so forth. As we entered the AI space, the big thing that we were building was credibility for end user tenants to trust that we could build this infrastructure stack. So we hired some of the largest GC equipment suppliers in the world to help build that credibility and help execute. As we've executed for these end users, we've built that credibility and in those discussions we started talking about our origination where we came from the capabilities that we really haven't been able to tap into on these projects because we haven't been able to use first principles design from the ground up how this infrastructure stack would work. And so that's opened a slew of conversations as people think about this capacity, as people think about this capacity on earth and space, how do you drive more efficiency, more speed? And so there is a next chapter there, George, that I alluded to in my prepared remarks, but we believe the skill sets and the philosophy that we built in a world where we were able to build infrastructure without constraints will be coming to light as well.
Various Analysts
Analyst Acknowledgements / Transcription Artifact
Super. Thank you.
Conference Call Operator
Operator
Your next question comes from the line of Ben Summers with BTIG. Please go ahead.
Asher Genoot
Chief Executive Officer
Hey, yeah, good morning, and thank you for taking my question. So I wanted to just ask a bit about the capacity that you guys moved under exclusivity. It says that, you know, you're looking across multiple regions there. So anything you want to highlight of particular, you know, regions of interest as we expand the power portfolio? Yeah, so when you look at the overall pipeline, one big ask that we received from investors was the understanding the pipeline and the makeup of that pipeline. We share the megawatt numbers, but we didn't share how many sites those were. We didn't share what regions they were kind of made up of. And so as you look through the disclosure this quarter, we shared kind of the average size per site. We also shared the makeup of what ISOs those sites are. And I think for most people, they'll see that we're very diversified. The thing that causes that diversification is we actually have teams dedicated to different regions to specialize in those regions and to dive deep within them as well. As we continue to scale, we have our greenfield origination team, we have our corporate development team. And so we're looking at projects across the board and as we think through the election cycle yesterday as well, diversification I think is increasingly important to be able to navigate through any policy or market volatility that may come up and we feel confident that diversification today.
Various Analysts
Analyst Acknowledgements / Transcription Artifact
Super helpful. Thank you for taking my question. Of course. Thank you.
Conference Call Operator
Operator
Next question comes from the line of John Todaro with Needham & Company. Please go ahead.
Asher Genoot
Chief Executive Officer
Hey guys, thanks for taking my question, and congrats on a quarter down here. I guess just going back to Texas and the election, and your comments around ERCOT and the December approval schedule, just wondering if you could frame up the confidence in that. My read would be, you know, maybe it gets pushed out and you get new directives from a governor, but you guys are obviously closer in Texas and with those regulators.
Sean Glennan
Chief Financial Officer
So just wondering on the framing of ERCOT confidence for the December approvals.
Asher Genoot
Chief Executive Officer
Going into the elections, we spoke to a lot of our consultants and lobbyists in regards to the different outcomes of the elections, how does it affect them. I think the thing that is really important is from day one, we've focused on building responsibly. And so even when the audit process came out, we were confident there because we had already answered the questions from the PUC that came out that were voluntary. Similarly here, we believe the mindset is not don't build net new investments into this Thank you, Asher. Thank you. Your next question comes from the line of Patrick Mulley with Piper Sandler. Please go ahead.
George Sutton
Analyst, Craig-Hallum
Yes, thanks for taking the question.
Patrick Moley
Analyst, Piper Sandler
So I just had one on the buyback, Asher. You said that you felt the shares didn't fully reflect contracted value or revenue and controlled power. So could you maybe just share how you frame intrinsic value internally? Is that an OI multiple? Is it some of the parts or something else? And then at what point do you think you could look to fund repurchases with cash or the revolver rather than Bitcoin, given that the stack has... I think it's a little under $700 million now. Thanks.
Asher Genoot
Chief Executive Officer
Thanks for the question, Patrick. So it's really a triangulation on intrinsic value because many people look at the company and value it differently. So the first mythology is we look at the sum of the parts. What are the three contracts that we've announced across the two projects? So that's Riverbend, Beacon 0.1, Beacon 0.2. What is both the net present value of those contracts, so doing the DCF, but also how do we think about the cap rates in different market scenarios that we'd be able to sell those projects and what they should be trading at. So that's existing projects. Then we have conviction over the four funnels that we have, whether that be the greenfield funnel that we disclosed publicly, the behind the meter funnel, the corporate development funnel, the new opportunities we're looking at and the brownfield funnel as well. And so that creates the kind of growth of where we believe the company can go and we apply discount factor to different projects at different stages. And so if we look at, I mean, where we're trading today, we're not even trading at the value of all three agreements, needless to say, even two of our contracts. And so we believe that we're trading even today, even more so compared to when we were in the seventies, a discount to the value of these existing agreements. They just come online and start operating on these triple net structures. Then we have all the growth that we have in plan and put aside Mark Eidelman, Michael, Asher Kevin Genoot The market has obviously had some negativity over the recent weeks. And so even though we may be trading under intrinsic value, we are focused now to make sure that we maintain capital preservation and optionality because there might be interesting buying opportunities that come up that never came up before because things were too expensive. And so we don't plan to continue to buy aggressively as we want to reserve that cash. In our revolver, we also don't plan to use a revolver for share buybacks. Really, we thought it was a really nice way to respond to investors over the last two years, which the main question we had around balance sheet was, how long do you plan on holding Bitcoin for? You're an AI company now. You don't get value for your Bitcoin at all. Why still hold it on the balance sheet? and as we looked at where the markets were relative to our share price and Bitcoin price, frankly, we had a lot more conviction in the appreciation of our stock relative to where Bitcoin price was as well. And so we swapped exposure from Bitcoin to HUD-H shares and initiated those buybacks.
Various Analysts
Analyst Acknowledgements / Transcription Artifact
All right, great. Thanks, Asher.
Conference Call Operator
Operator
Your next question comes from the line of Logan Hennen with Northland Capital Markets. Please go ahead.
Sean Glennan
Chief Financial Officer
Hey, morning, guys. Thanks for taking our question. Just one from us today. Can you provide some additional color around the new 230 megawatts acquired in West Texas in regard to how you were thinking about that opportunity and maybe clarify where that site sits in batch zero and the remaining permits and approvals needed there?
Various Analysts
Analyst Acknowledgements / Transcription Artifact
Thank you.
Asher Genoot
Chief Executive Officer
Happy to do so. So we were part of a bankruptcy. It was kind of a deja vu in 2022. We were part of many bankruptcies where we acquired assets during the downturn in and the crypto market. And we were able to acquire many infrastructure projects, whether that be full acquisitions, taking on managed services agreements or being planned sponsors, spin out new companies like Ionic. And so it was a very informative journey in our lives. And when we were part of this bankruptcy auction, it was a little bit of a deja vu back then. We grew almost 10X during that period of time as a company. And so building during market downturns, we see as really interesting opportunities to grow because things are really cheap. It's never as ideal to build when things are expensive. It's always much more exciting to build at a lower cost basis. and so I think this was the first opportunity in the market that allowed for that. We've been patient, we felt like at some point the opportunities like this would come up and one of them did come up so we pursued that opportunity. That site is located, those two sites are located within driving distance of our Salt Creek campus in West Texas. You have sites there in power for the Bitcoin mining sites that were there that are energized right now or that are energized. They don't have miners there that were hashing because through the bankruptcy those hosting clients left. And so we visited those sites last week and we are working through the closing conditions now and look to close by end of year.
Conference Call Operator
Operator
Your next question comes from the line of Richard Cho with JP Morgan. Please go ahead.
Richard Cho
Analyst, J.P. Morgan
Asher, I just wanted to ask, as you've gone through this deal with the leading AI company, how has the change orders and the engineering changed? And how has HUT kind of been able to maximize your ability to address those needs? Because I think the ability to build these large-scale AI data centers is underappreciated and just wondering what challenges that you've been faced with and how you've handled them.
Asher Genoot
Chief Executive Officer
Appreciate the question, Richard. I'll answer that question from two mindsets, current status quo of the projects we're building and net new approach towards building that I've talked about a bit on this Q&A and the prepared remarks. And I'll go through a little bit of a kind of flow chart of the different areas in which you move through them. So the first thing is a change order comes in. And that change order may be driven by insurance need, may be driven by customer needs, whatever it may be. And if you look at a site like Riverbend, there are a lot of counterparties involved, right? Our end tenant is Fluidstack. Then you have Anthropic as the end user. You have Broadcom and Google who are part of kind of the credit profile. We have Jacobs as our GC, there's subcontractors, there's Verta. So there's a lot of parties in the mix in here. So any change order kind of has to run through the system and through all these various parties in many instances. And so the first question is when a change order comes in, is that a change order that is necessary or not is the first question, right? So there's discussion around What is the ultimate thing that is trying to be solved for? And is this the best way to solve for it or not? The easy thing is say, okay, you gave me a tenant change order. This is the time impact. This is the schedule impact that we've received from Jacobs. Here you go. Thank you. And do you want to pay it or not? We think that that starts to have a very big creep situation where things creep up because you just take it for gospel. And so we start with kind of challenging the first principle, working together across all of the partners and saying, what is the ultimate thing that we're solving for and is there a more efficient way to do it without impacting schedule and cost? Because ultimately, schedule and cost, if we didn't do that, just gets passed through to the tenant, but we want to drive infrastructure coming online as quickly as possible. So then, if we get to a place where a change order is necessary, whether it be change in requirements, change in design, whatever may be that causes that, then the question is, What can we do to be able to minimize the impact of that change order? And once you get to that final kind of answer, everyone's aligned on this is the change order that's necessary and this is the impact that it has, then there's kind of a slew of questions that arise. The contracts currently have it so change orders need to be paid back in cash, reimbursed in cash. The schedule impact applies to the least kind of peri-pursuit with whatever the impact is. and you get a fee on top of that for managing the process. There's obviously increasing questions from end users, which is, hey, can you rentalize this? Rather than it being just a CapEx reimbursement that we pay for, can you rentalize this or not? So I think when you think about that, there's really kind of multiple ways to think about that. One is, is there ample ability within the budget to be able to rentalize it that is within the financing guardrails that we have built towards and the contingencies that we've put in place? great, you get more yield on the capital stack that you have. The second is if that doesn't exist, can you use external capital or additional kind of funding in order to do so? And we've seen that in other parts of the market as well. And if you look at it from an individual investment, depending on what kind of yield on costs is agreed to on the rentalization, it could be really interesting depending on your balance sheet position, your willingness to take on that return on investment. Obviously right now, were investing into these projects and have pretty good structures, LTCs and so forth. And so that bar is pretty high. But overall, that's how we would think about in bucket one, which is that kind of the current regime with many counterparties and really these bespoke, unique solutions. And there's a lot of engineers involved and people have different opinions and kind of in driving and that caused design changes. The second bucket is going back to kind of first principles, Vega and so forth, which is what is the thing that we're trying to solve, which is bring on reliable compute at speed and at scale. And so there is a second kind of camp in which we've been having a lot of discussions around, which is, can we get aligned from a leadership perspective within HUD-H, our tenant end users, et cetera, that we align on the thing that we need to build. And if we're able to build it really quickly, we don't allow for that many changes along the way, because those are the things that really slow down and kill a project. And in that scenario, I mean, you're building much more like a SpaceX where you're building at speed, you don't have as many cooks in the kitchen making decisions and you have kind of a set thing that everyone's aligned on upfront and you sprint at getting that infrastructure stack online. And so Richie, I hope that was helpful. I'm walking through kind of like status quo of industry and then how do you actually bring those in so then you're not on call talking about kind of those impacts and it requires a certain type of partner philosophy and conviction and confidence in the ability to build with first principles.
Richard Cho
Analyst, J.P. Morgan
That's great and honestly I think the problem is people don't realize how this is a problem at scale that you need to engineer for and everyone just thinks it's easy to build and it shows level of detail that is needed to deliver the amount of capacity at scale.
Asher Genoot
Chief Executive Officer
I'll give you an example. If we go a little bit more granular, we had a request to change some of the lineups because there was a different chip set and design that was going in. And at first, when we kind of asked for those requests, the thing that came back was the impact and schedule and cost that we believed was too high. And so we really dove deep with our – equipment vendors, and GCs, and we said, what is driving this? Because if everything's passed through, as a developer, we can just pass it through to the end user and say, you asked me for a change order, this is what we got back, and this is the change. But as we think about the importance of trying to bring on compute quickly, and we can't do this across all the board, but there, the big reason was having to go and change basically the cable trade that have to pull more cable across the facility in the short months to be able to get them into the actual TPUs. And so we looked and we said, okay, why do we have to actually increase the size? Why do we have to go re-engineer all of those skids? Why do we have to increase the sizing? Is there a way to do that in the field so we're able to save on schedule and cost? And we were able to reduce that cost impact by over 90% by just challenging and focusing on how do we engineer this in a better way. And so Richard, many of those situations come across alongside large bills and being able to navigate and manage through those with your end users and all of your partners is critical.
Various Analysts
Analyst Acknowledgements / Transcription Artifact
Great detail, thank you.
Conference Call Operator
Operator
Your next question comes from the line of Chris Brendler with Rosenblatt Securities. Please go ahead.
Richard Cho
Analyst, J.P. Morgan
Hi, thanks for the morning and thanks for taking my question.
Asher Genoot
Chief Executive Officer
I just wanted to see if there was any way to think about Louisiana versus Texas, given the election results? No change with the governor in Louisiana. I know that it seemed like a very supportive community when we were down there last month. But how should we think about your future expansion plans in relation to the election results? For the folks that had the opportunity to come to our Riverbend First Look ceremony, the governor was there, the local community was there. were very proud of the relationships that we built and the support that we've garnered throughout the state and the adoption we've had and HUD-AID's ability to build responsibly. And so we're big fans of Louisiana. We were before people even focused and looked at Louisiana. We were locked out of rooms two, three years ago when we talked about Louisiana. There's a lot more focus today, but we continue to double down and focus on the state and are very proud of the work that we've done and are excited to continue to invest and continue to grow within the state as well.
Various Analysts
Analyst Acknowledgements / Transcription Artifact
Great.
Asher Genoot
Chief Executive Officer
And then just a quick follow-up on the sort of buyback slash, you know, sort of capital needs question. I sort of understand the balancing act there, but, you know, how do you view the current Bitcoin balance in relation to cash needs? And it just feels like not quite the right time to me to be, you know, sort of leading into a buyback. So just I'd love a little more color on how you're thinking about your cash vision of the near term given market conditions.
Nick Giles
Analyst, B. Riley Securities
Thanks.
Asher Genoot
Chief Executive Officer
Really appreciate the question. I'll start with the buyback itself and talk about our liquidity position. So in regards to the buyback, we've increased the buyback, not necessarily to buy immediately, but to hold that optionality. When we first announced a $250 million buyback, that was almost two years ago or so at this point. And we really only initiated that in the recent quarter. And so we just sat on that opportunity. So similarly here, and expanding the buyback is less around we want to go buy billion shares immediately. As I mentioned, kind of liquidity and being able to invest in opportunistic moments is critically important and especially in these market conditions. So we don't expect to go and immediately go buy shares off the back of this increase, but rather just leave it on the shelf as an additional tool that we have. Our overall liquidity, if we think about on the parent level and across the projects, is over $7.7 billion, and that's across our Bitcoin, the cash we have, the restricted cash we have on the project level that finance those projects, and the revolver that we put in place as well in the availability along that revolver. So we are excited and confident with that access to that capital that we have on our balance sheet in our bank accounts. We also have zero recourse debt at this point on our balance sheet as well. And so the increase of the share buyback is to have on the shelf and not to implement immediately because we believe that cash will be king as we navigate through this current volatility. Awesome. Thanks so much. Congratulations on all the progress.
Various Analysts
Analyst Acknowledgements / Transcription Artifact
Thank you.
Conference Call Operator
Operator
Your next question comes from the line of Nick Giles with B-Row Securities. Please go ahead.
Nick Giles
Analyst, B. Riley Securities
Yeah, thanks very much. Maybe just a question for Sean. Curious on how the way you're approaching structuring any future debt deals has evolved since your last raise, or can you just give us a sense for some of the alternatives you're exploring or any kind of features of a debt offering that you might be considering today that weren't as logical, you know, say six months ago? Thanks.
Sean Glennan
Chief Financial Officer
Yeah, thanks, Nick. Appreciate the question. So look, I don't think we actually view how we approach financing any differently from the way we did the last two. We start with a clean slate every single time. We say, what is the asset we have? What are its attributes? And what do we think is the financing that it deserves? We obviously also take a look at the market environment. How are different markets performing? Where is their most depth of capital? Where do we see the most liquidity and best pricing? And then we also think about, you know, what's going to increase the free cash flow yield of these projects on a risk adjusted basis, as we talked about in the preparative mark. So I don't think the approach actually changes at all. It's like everything we do at the company from a first principles perspective. We have been preparing, you know, for the financing for Beacon Point 2, which I think is kind of what you're alluding to for a while. And we have, I think, really great solutions that we're going to bring to bear some of those might involve things we've done before, but they don't necessarily. But we've been working pretty tirelessly to make sure that we have a great path. I think we got a lot of kudos for the prior financings we've done, and we're not resting on our laurels. We have a very, I think, clear path on what we want to do, how we want to finance, and a couple things aren't going to change. One, recourse to the parent. and two, we're going to try to minimize as much refinancing risk as we can. So again, approach doesn't change. I think some of the instruments and tools we use might, but we'll keep that for the day when we finally, we do announce our financings because we don't want to obviously forerun any transactions.
Nick Giles
Analyst, B. Riley Securities
Appreciate that clarification, Sean. I'll turn it over, but continue. Best of luck.
Various Analysts
Analyst Acknowledgements / Transcription Artifact
Thanks, Dick.
Conference Call Operator
Operator
Your next question comes from the line of Dylan Hessland with Lucid Capital Markets. Please go ahead.
Dylan Heslin
Analyst, Lucid Capital Markets
Hey, thanks for taking my question. On the Beacon Point Phase 2 lease amendment from 15 years to 17 years, could you just provide a bit more color on how you're looking at that? Like it seems like you mentioned higher financing cost. Is that an interest rate look through or is that a potential combination of both the CapEx flowing into a higher bond stub that you need and thus interest rates. Does that still mean that to your amendment still doesn't eat into any of the extensions, correct?
Asher Genoot
Chief Executive Officer
That's right. That's exactly right. It doesn't eat into any of the extensions and really it was a holistic discussion over the site and I think there's a big question that folks have asked which is if there are changes in market conditions, how did the tenants respond to that? And at the end of the day, the data center costs are still relatively small to the overall compute economics and the value of those economics. And so for us, I think this is a signal and a sign that whether it be through tenure rates, et cetera, that tenants understand market conditions and are willing to support to make sure infrastructure gets built.
Various Analysts
Analyst Acknowledgements / Transcription Artifact
Great.
Conference Call Operator
Operator
Your next question comes from the line of Brett Noblak with Cantor Fitzgerald. Please go ahead.
Brett Knoblauch
Analyst, Cantor Fitzgerald
Hi, guys. Thanks for taking my question on this wonderful morning. I just want to hit on Texas one more time. Obviously, kind of the outcome we weren't expecting. When we read through maybe the incoming governor's previous stance on data centers, it doesn't feel like she's actually like super against them. It's not a hard line, no data centers. It seems like she's in line with the rest of the country in one kind of data center operators that pay for grid infrastructure, water infrastructure to save rate payers, local communities to have kind of a say in what's happening. How different do you view the Texas landscape today versus yesterday? Is it more of the same? Should we assume that most tenants now are gonna be looking outside of Texas? just any additional color would be helpful. I really appreciate it.
Asher Genoot
Chief Executive Officer
I agree with you, Brett. We believe that this infrastructure is an American initiative. It is not right or left. And whichever side you're on, making sure that citizens don't get impact in their day-to-day lives in terms of their energy, their water, their status quo, their lifestyle is critical. the way that we've been building has been with that mindset and that approach, right? If you look across the states in our development pipeline, I mean, there are states before last night that had democratic leaders within those states and we've continued to explore and continue to push forward on those developments of those projects because we believe we have a program that's focused on building responsibly. And so as a result, in Texas. We don't actually think this changes much of what the governor-elect is looking to do because we're very supportive to make sure that citizens are protected while America is building this critical infrastructure. And so we're excited to work alongside her and her administration to make sure that Texas can lead the front as well in terms of building this infrastructure and having these investments go into the state responsibly. So my perspective is similar to yours, Brett, and we continue to focus on that foundation regardless of people have asked for it or not.
Conference Call Operator
Operator
Really appreciate it.
Various Analysts
Analyst Acknowledgements / Transcription Artifact
Thank you, guys. Thank you.
Conference Call Operator
Operator
That concludes our question and answer session. I will now turn the call back to Asher Genoot for closing remarks.
Asher Genoot
Chief Executive Officer
As we have built this business, we've always understood that periods of rapid infrastructure growth come with volatility. And there will inevitably be peaks and troughs driven by both broader macroeconomic conditions, but also industry dynamics. And what has always mattered to us is building a business that can not only withstand these cycles, but also continues to grow and execute through them. And that is why we've been so deliberate in strengthening our balance sheet, structuring our business thoughtfully, and building a foundation design for long-term success. So as I shared last quarter, our excitement and conviction in the business we are building remains as strong as ever. We know there will be challenges along the way, but we're confident in our ability to navigate through them, overcome them, and emerge stronger. And I reminded our team in our last town hall of Warren Buffett's famous observation that the market is a voting machine in the short term and a weighing machine in the long term. We can't control short-term market conditions, but we can control how we execute, how we allocate capital, and how we build this company. Our focus remains on what has always mattered most, executing on our commitments, delivering for our customers, and building a business that can compound value through every market cycle. We believe the opportunity ahead of us is extraordinary and we remain as committed as ever to realizing it. Thank you all for being with us today.
Conference Call Operator
Operator
Ladies and gentlemen, that concludes today's call. Thank you all for joining. You may now disconnect.