Good morning, ladies and gentlemen. Welcome to Sigma Lithium 2026 third quarter earnings call. I would like to inform you that this event has been recorded, and all participants will be in Lithium-lony mode during the company's presentation. A recording of this webcast will be available on the company's website. After prepared remarks, there will be a question and answer session for participants. At that time, further instructions will be provided. I would now like to turn the conference over to Ana Hartley, Vice President of Investor Relations. Please, go ahead.
Ana Hartley
Vice President of Investor Relations
I would like to welcome you to our third quarter 2026 earnings conference call. Joining me on the call today is Ana Cabral, Co-Chair and CEO of Sigma Lithium and Felipe Peres, CFO of Sigma Lithium. I would like to remind you that some of the statements made during this call including any production guidance Thank you, Ana. So, here we begin our third quarter.
Ana Cabral
Co-Chair and CEO
of 2026 earnings presentation. We have disclaimers as we will be making a number of forward-looking statements, and therefore, without further ado, I'll get into the presentation. Well, Sigma, for those of you who don't know us in the audience, we're the largest mineral industrial concentrate producer in the Americas. We are low-cost. and we have been self-funded since we began production in July 2023. There are three key points about Sigma that make us quite unique. First is our resilience, which was demonstrated in the third quarter. We have financial discipline, which drives us towards the low end of the cost curve, creating a low cost advantage. Our strong cash flow generation has enabled us to be self-funded since July of 2023. That's resilience. We have scale. We have a projected production of 330,000 tons for 2027 with the current installed capacity. Our team has proven execution capabilities and quite a lot of experience, and we have just primarized our mining operations. We also have significant growth profile. We can double and then triple capacity with quite a low capex. We have incremental industrial capacity to build. There are two more plants to be built. There's a second mine to be opened. The capex for each of the incremental industrial lines is approximately 100 million US dollars, and there's zero existing capex. So very low capex to double and then triple industrial capacity with the extra backup of one more mine feeding material into those two plants. So three key characteristics. In addition to that, we have been low cost since inception, which gives us tremendous resilience throughout lithium price cycle volatility. During the third quarter, our calibrated execution steered the company. It was the demonstration of our resilience. We resumed operations successfully twice during the quarter. This is an operational prowess because we had to demobilize and mobilize 1,700 people plus equipment twice. We've also achieved landmark victories for ESG credentials, giving a positive visibility to the prosperity wave, earning a status of too big to stop in our state. More importantly, we've delivered a pivotal debt refinancing. We issued a five-year, $125 million convertible debt at the money, which significantly delivered and lengthened our debt profile, giving us breeding room for the next stage of growth. We've also maintained tremendous financial discipline. We delivered high net revenue margins of 32% and maintained a low CIF cost of $518 per ton, even this quarter. More importantly, we're now fully focused on executing our production growth strategy for 2027 and 2028. Throughout the quarter, we maintained our top global safety record, Thank you for joining us today. and Howard Maintain Safety. Our TRIFR is zero, which makes us extremely proud, demonstrating our operational prowess. So without further ado, I'll go straight into the financial highlights of the third quarter of 2026. This slide demonstrates the financial discipline we achieved during the third quarter of 2026. Our low-cost leaders delivered robust net revenue margins. First, we delivered a total debt refinancing which lowered our short-term debt by 85%. All we have left for the next 12 months are trade finance lines and development bank debt. We maintained our high margins. Our net revenue margins remained In the 30s, at 32%, and we maintained a 57% net revenue margin for the nine months ended in the quarter. Our adjusted EBITDA margins was also very robust for the nine months ended in the quarter, demonstrating the remarkable resilience of Sigma even during the third quarter when we were mostly stopped. Our discipline also was key to maintain our low-cost leadership. We're still delivering in Asia at a $518 CIF. Our all-in sustaining cost is at $642. So when you compare that with current lithium prices of about $1,200, one can see that we still have A vast room for margin and cash flow generation, which is our unique competitive advantage. Our gross revenues were down because we were stopped for about 65% of the quarter. However, on a nine-month basis for 2025, we were at $115 million of revenues, up 20% if compared with last year on the same period. Again, a demonstration of remarkable resilience. This slide is all about our low costs, and it just demonstrates how the discipline created this competitive advantage. There are our low production costs. Plant gate cost, it was $424. Then at port in Asia, We have a CIF cash cost of $518. Now, on the right, we compare all in sustaining costs with the realized lithium prices for the quarter. And that's where one can see the vast room for cash generation. And even if one contrasts these two numbers at today's prices, one would still see the advantage of low cost. Our all-in costs were $642, and the average realized prices just yesterday were $1,200. So again, significant cash flow room. This slide demonstrates how we are the cost leader. We are resilient to lower price pressures of new processing regions in Africa, and we Lower price pressures from innovation in brine. Sigma is the floor. Our costs, both on the CIF basis and all in sustaining costs, are lower than Africa, which gives us tremendous competitive advantages in an environment where lithium prices are volatile. So we have shown guidance that's essentially on track. as we have shown in the third quarter earnings preview. We adjusted the line on the chart to demonstrate that at current prices, at yesterday's prices, compared to our CRF costs, we have $662 off room. So that is essentially resilience quantified. The next slide has the dissection of our earnings and our results. On a quarter-to-quarter basis, one can see that we have delivered stronger margins compared to the same quarter of last year at 32% net revenue margins. That's essentially a result of our flexible cost of goods sold, the ability the company has to adjust variable costs. The same goes for cash flow. Our cash flow generation is tremendous. When you compare the third quarter 25 versus third quarter 26, the numbers speak for themselves. And we ended up in the third quarter 26 with a higher cash position than in the same quarter of the previous year. The operational cash flow generation was $24 million. And again, tremendous for a quarter where we have been stopped for most of the quarter. When one compares On the right side, the nine months versus nine months is when these numbers jump out of the page. Nine months 26 versus the same period of 25 basically shown a net revenue margin catapulted to 56%. When you look at cash flow and cash flow generations, the numbers are tremendous. We show an operating cash flow of $51 million. and a cash position of $10 million, which again is a demonstration of tremendous resilience when we have stopped for most of the quarter. On the next page, we actually break down the cash flow generation. So third quarter 26 versus the nine months of the year ending in the third quarter. We have, even in the third quarter, obtained net inflows of $4 million and ended the quarter with a position of cash of 10 million U.S. dollars. Then, when you look at the full nine months, same thing, although you see the stronger net operational cash flow generation at 51 million dollars. Going forward, we have a very comfortable pipeline of contracted sales, so we have had Thank you very much. mostly because of the resilience of the results achieved in the first quarter and on the second quarter. This slide demonstrates the significant cash flow that a company can deliver at current installed capacity. We're forecasting 240,000 tons for the 12 months forward. At those levels, even at current lithium prices, we can deliver Approximately $128 million of cash flow. When one looks at the forward production we are forecasting for 2027 of 330,000 tons, at current prices, we are expecting to deliver approximately $191 million of cash flow. These are robust levels. and again, a direct result of our low all-in sustaining costs. So, one more demonstration of operational resilience enabled by the low costs. This slide demonstrates the effect of the pivotal five-year debt refinancing on our balance sheet. We issued a $125 million convertible note, which had a transformational effect on the debt profile of the company. Essentially, this convertible note also creates the potential for the leveraging because it's almost at the money. The proceeds were mainly used to pay down upcoming debt maturing in December of this year, and that debt was essentially transferred to November of 2031. So it smooths out our debt maturity profile, matching that with upcoming cash flows. On the right, when we look at the picture of the third quarter static, one can see that the pro-former operating cash flow for the year, assuming we would annualize the nine-month 2026 cash generation, would still give us a low leverage ratio. But the current issuance lowered it even further. This slide shows how transformational the five-year convertible note was for our future growth plans. It creates low leverage ratios, essentially enabling us to create borrow capacity. So here we show the low leverage ratios, even at current lithium low prices. Connecting to the cash flows we showed earlier, At the two levels of forecasted production, one can see in yellow the leverage ratios with the convertible note unconverted. And in green, the leverage ratios of the convertible note converted. It becomes negligible. So, at either of the production levels we forecast, 240,000 tons for the next 12 months or 330,000 tons for 2027, we end up with very low leverage at $1,200 per ton. So the next page demonstrates the borrowing capacity opened up by this pivotal refinancing. And here we pro forma the convertible note again, converted and unconverted. Even converted, At low levels of lithium, we averaged out the cash flows. We end up at two times with extra room for borrow. Let's say at 2027 forecasted production levels of another $170 million. And at three times leverage at 2027 forecasted production levels at $330 million. So we delivered the balance sheet. and even with the convertible notes in there, at regular leverage ratios of two times or three times, we have ample room for borrowing. Clearly, we would not borrow in a rate that's not conducive to the nature of our business. So, if we were to re-gear the balance sheet, we will do that with what we call adjusted debt, meaning project finance debt or development debt. But nevertheless, these are the raw numbers, and we wanted to stress this because it shows how pivotal the note was. This slide basically talks about the underpinning variable that's going to drive lithium going forward. The demands are consistent. The entire market is very aligned in the fact that lithium-demand is growing and growing robustly. However, prices are not driven by demand. They're driven by this low-cost supply coming out of regions that are not necessarily formal. So, the challenge for us producers is to remain resilient to match those prices. And this is what Sigma has demonstrated throughout this presentation. When you look at the impact of African production, there are three key variables. First is vertically integrated with the supply chain, so it continues to produce and deliver even during price downturn, almost in price agnosis. Then you have the phenomena of low-cost DSO or low-concentrate DSO, where the material gets to the client almost at cost, given that the client is financing the production. So the only curbing is the downward pressure of high logistics costs. And then you have the full concentrate production coming out of countries like Zimbabwe and Mali. Those are formal and they're integrated into the supply chain. So they come in an LCE equivalent of 7,000 to 13,000 kilotons per ton. In other words, very competitive pricing. So here at Sigma, as we described, we are the floor. So these prices don't worry us because even with this pricing environment, we can compete and we can deliver significant cash flow. Today, for instance, prices are about $1,200, which gives us ample room to deliver cash flow. So that's the importance of resilience is the fact that going forward, lithium pricing will continue to remain volatile as demand demonstrates tremendous growth throughout the next couple of years. Now we go into the production capacity and what we see as the 2026, 2027 operational outlook. This slide demonstrates how Sigma will deliver the forecasts. What we are forecasting for the 2027 year is not different than what we have already delivered since the upgrade of our industrial plant in the fourth quarter of 2024. The plant has two circuits, the reprocessing circuit and the main circuit. The total production capacity amounting to approximately 82,000 tons. In the fourth quarter, 24th, we delivered 77,000 tons. So that's industrial capacity. From then onwards, we delivered approximately 68,000 tons every single quarter. And if you annualize the third quarter when we decommissioned the contractor, it was the same exact number. Then in 2026, we entered the primarization phase. and we quickly reached the targets on the second quarter. The third quarter, we were stopped, but again, we demonstrated tremendous resilience to just bounce back and pick up where we left off twice. We remobilized and demobilized our entire contingent twice. So when you look at the picture of the third quarter, it's essentially a company in motion because we have 21,000 tons of inventory and 7,000 tons of production. Now, entering the fourth quarter, we have an additional 11,000 tons of production of high-grade. Going forward, as we catch up with removal of overburden, we're going to be well on our way to deliver on our projections. This page gets further into the details of the reprocessing circuits we talked about on the previous page. where we've shown that we can deliver approximately 15,000 tons of high-grade material coming out of the circuit. This is a circuit that's separate from the main high-grade circuit. It has its own dedicated cyclones, its DMFs, and it essentially upgrades the fines into higher-grade material in an automated process. So that we achieve 100% circularity, but more importantly, we deliver more lithium with the same mining footprint. That was the key to the upgrade of the lithium industrial facility, going from an average of 60,000 tons per quarter into 77 plus up to 82,000 tons per quarter, the reprocessing circuit. That is the 100% circularity we strived for. making us able to meet the recycling criteria of the European Union because our lithium has recycled material. Same mining footprint, more lithium. This page essentially shows how the cleantech plant upgrade enables 100% circularity. The amount of concentrate is essentially larger with just that one plant. In other words, in the fourth quarter of 2024, the plant delivered 920 tons a day. What we're forecasting going forward is kind of in the same magnitude, at 950 tons a day. So nothing different than what we've been delivering. And that's, again, the 15,000 ton extra coming from the reprocessing circuit. It's more lithium concentrate with just one plant. Here is the mining. So we're focusing now on increasing volumes during the fourth quarter to compensate for unremoved overburden that stayed put during the third quarter. We're going after the same section of the pit shell design in order to access this larger amount of high-grade material. So this is the south of our south pit. In other words, there's approximately 200,000 tons of Concentrate the equivalent over here, a volume of approximately 1.1 million tons of ore. And that's the goal for us in the next month or so, getting to that material, processing and converting that into concentrate. On this page is how we plan to deliver it. We're doing a second round of fleet upgrades, bringing in larger excavators and larger trucks. The excavators deliver an additional 40% ability to load up the trucks, and then the trucks deliver a 25% increased ability to haul material. So the second stage of deployment of large equipment is essentially a result of the primarized and upgraded mining operations. And again, we do more haulage with fewer amount of equipment, less diesel, more efficiency. And that's a result of our partnership with Sunny China and our equipment provider. We have decreased lead times for equipment availability and larger equipment available for us. Wrapping up this section on operational delivery, we want to delve into achieving the landmark victories of our impeccable environmental and social credentials. Minas Gerais delivered the verdict that SIGMA is too big to stop. We achieved this institutional visibility to our economic impact at Vale do Jequitinhonha. Rule of law has upheld our licenses and operations. So it was the institutional strength of Minas Gerais and Brasico. Rule of law, swift resolution to the stoppages. We were awarded a tax in record time, and we were awarded a classification of too big to stop. And then limited financial exposure, given that we didn't have any additional royalties or any, essentially, burdens levied on the company. But more importantly, we came out of this with a positive engagement with the state administration, and with the federal courts demonstrating the number of jobs at risk and the number of family members that would be vulnerable if SGMA wasn't operating. We have over 19,000 jobs connected to us directly. It's a shared prosperity business model. And out of these jobs depend 80,000 people. So this is essentially the too big to stop. These are SGMA fuel jobs. Half of them come from our social engagement, social inclusion programs. Here is the object of one of the conversations, the TACI. Ultimately, we demonstrate here that we adhere to the highest global mining standards with our quintuple zero, fully traceable lithium. If you look at other G7 countries, you can see their high standards. There's a tailing dam to high standards in a country, and there are overburdened rock piles to high standards in another country, both G7s. When you look at SIGMA and our rock piles, they have the same standards of a G7 country rock pile and they have GRAS, active germination, which was our element of delivery in concomitance with the TACI. We agreed to a million dollars of active germination to be delivered throughout the next year. Concluding the presentation, here are our priorities. We plan to continue to execute and achieve the re-raising. First, the milestones for 2027. We're going to continue to ramp up mine one. We're going to deliver on the growth and we're going to unlock the full potential of phase two in stages, in a disciplined, Organized Execution. First, continuing ramp-up of Mine 1. We plan to deliver 240,000 tons in the next 12 months. We're going through a second round of fleet upgrades to enable more haulage, and we plan to deliver 330,000 tons in the full year of 2027. Second, growth. We plan to resume Phase 2 growth plan with a new mine opening. In other words, we're going to resume phase two, bottom up, opening a new mine. We're fully funded for the capex of opening a new mine by the current cash flow generated by the existing industrialized. Why did we start by the mine? Because it's the largest job creation. That's how we bring the most amount of prosperity to Vale do Jequitinhonha. A new mine means Another 25,000 people connected to SIGMA. 6,400 indirect jobs. And that's without the social programs attached to it. Then we will resume Plan 2 construction. So with that, we would plan to get to 580,000 tons of capacity, which will bring in more job creation in the region. So unlocking the full potential of phase two. If we stopped at the mine, if you would add this number of jobs to the current jobs we have, we would essentially, following opening a second mine, have 100,000 people connected to our operation at Vale do Jequitinhonha. In other words, the potential for prosperity is tremendous. and that is why we have tremendous support from the newly elected government of Brazil and Minas Gerais. And here we have the magic. It's low cost plus cash generation. So we're very well positioned for re-rating. They're companies that have the same production that we have and that traded double our value. We do believe that as we continue to execute The re-rating will come up gradually and this is why we're so focused and we maintain our discipline. And with that, I'll conclude and shall pass on to Q&A.
Conference Operator
Operator
Thank you very much for the presentation. We will now begin the question and answer section. To ask a question, please submit your question using the Q&A button on your screen. Please provide your name, In the name of your company, for your questions to be taken. Our first three questions comes from Olin Chan from Hotwind. With Q3 production falling to just 7,293 tons, how did unit cash costs remain so low? Were shutdown related fixed costs excluded or capitalized? This is the first question. The second question is, regarding the US$120 million convertible notes, are there any provisions that allow the company to render or repurchase the notes earlier to avoid shareholders dilution? If so, could you please explain these provisions in detail, including any conditions, restrictions, or early redemption penalties? And that's it.
Ana Cabral
Co-Chair and CEO
So, I'll answer questions one by one. First, it was regarding the costs. They were nor capitalized nor excluded. They sit as an expense line together with other operating expenses. There's a note specifically dealing with this, which is note 24. So those costs amount to $13,376,000. And essentially, these are what we call idle capacity costs. The note provides quite a lot of detail about it. And that's how IFRS would dictate us to account for these costs. The second question is related to the convertible bond. Yes, there are provisions for early redemption and for early payback. It's a known call, don't put three. So by year three, we could actually call the convert and redeem the bonds. But the actual intention is to let them convert because we have not diluted since 2021. We're very calibrated in the way we plan dilution. So investors can start converting after month 12. And we believe that given where the shares were, where the shares are, the investors perhaps will convert these bonds into equity, which will relieve the balance sheet, as we've shown in one of the slides where we simulate leverage ratios with the conversion. Again, investors can start doing that after the first 12 months. And there's a put on year three by investors for the bond. The same way we have a call on year three for the bond.
Conference Operator
Operator
We have one more question from Olly Chan for Hotwine. Sigma Lithium has been listed on the ASX for more than two months, but there appears to be virtually no trending activity or meaningful share price quotation. What is your view on this situation? Why was the Australian listing failed to attract What specific steps will the company take to improve liquidity and attract Australian investors? Without activity training, how can the ESX Listener achieve its intended purpose?
Ana Cabral
Co-Chair and CEO
Absolutely. And the convertible bond note that I was just referring to in the previous answer is the answer to the question. When we listed in Australia, our commitment was to deliver or to execute in the ASX every single wish once the company would do thereafter. So the convertible bond is converted into CDIs, which are the ASX listed shares. So we do believe that when conversion takes place, initially beginning 12 months from now, that ticker, that CDI security will begin to have quite significant liquidity resulting from the converted shares of the bond. Again, the dilution was approximately 14%, so there's going to be a number of shares that, when and if the bond is converted, will flow into the ASX market, hopefully beginning the trading activity you referred to. We're doing our part to act on that listing in order to foster the liquidity and the trading, and the note was a demonstration of it. Our first instrument issued was already –
Conference Operator
Operator
The next question comes from Katie Lachapelle from Canaccord, Genuity. Hi Anna and team, thanks for taking my question. I want to clarify your comments regarding debt. Is the plan that repay the synergy debt before year end, instant off in 2027, but then also bring an additional debt?
Ana Cabral
Co-Chair and CEO
Katie, well, thanks for the question. Good to see you. Yes, that's exactly the plan. We decided to do the conversion because the refinancing of the debt saves us quite a lot of cash. With the debt reset and the interest rate increases of SOFR, that debt would end up almost in 14% following the reset in December. So, our decision is to pay the debt immediately after the issuance of the convertible bond closing. We'll pay the debt immediately after the convertible bond closes. which is imminent. So essentially Synergy will be completely repaid and removed from our balance sheet. And therefore the balance sheet becomes an encumber because Synergy is a secure creditor. The plan going forward as we've mentioned a few times is to re-leverage the balance sheet for the growth strategy. And that will be done with what we call adequate type financing. In other words, as we As we bring in more debt for growth, we plan to bring in long-term, low-cost debt along the same lines of the BNDES debt that we have. So, most likely, once we begin this new stage of growth in 2027, we will unlock that credit line in order to tap from it to deliver the growth.
Conference Operator
Operator
We have one more question for Katie. Hi, Ana. Can you provide more specific timelines around the plan and growth at Phase 2? When we will open the mine? When you plan to construction components or procurement for the Phase 2 plan components? Thank you.
Ana Cabral
Co-Chair and CEO
Yes. We plan to start opening mine too shortly, very shortly. Most likely, it will be first quarter of next year or later this quarter. Now, that will be the foundation of planning for the second plant. We have initiated the construction of the second plant in December 2024. We used quite a lot of our liquidity on it. We continued throughout the first quarter of 2025. So, what's remaining is procuring for equipment. We've had a procurement sheet. and we estimated based on that procurement sheet updated that there's approximately 80 million US dollars left of equipment to be ordered. We do not plan to do it now. We do plan to do it most likely early in the Next question comes from Rock Wolfman from J.P. Morgan.
Conference Operator
Operator
First, can you speak to the market dynamics around lithium tailings right now given lower lithium pricing dynamics? It is still a liquid market and would it be possible to sell the full 15,000 tons in the Q quarter or will this material liquid need to be reprocessed to high Great to be sold.
Ana Cabral
Co-Chair and CEO
Both things. It is possible to sell it. The lithium tailings market now looks a lot like it did almost a year ago when we made the decision to go and primarize the mine. X works price for that material now hovers between $30 to $50. So that's a net profit. I would say depending on the lithium quantity of the material, you would have a different ex-works price. What we got on the plant probably will command a higher price of around $50-ish, perhaps even higher. We typically do not sell tailings against a falling lithium price as we've been observing in the last two weeks. So we'll stay put and wait further into contract season to make a decision about the tailings. Even though, ironically, this is when we get the most amount of offers because that product is very profitable for the client. Essentially, the client just transports it out and throws it into a flotation plant, converting it into very high-grade lithium concentrate. And an example is what's happening with a lot of the African content, which comes out in similar format and becomes very profitable on a fully integrated basis for the battery makers. Some of these producers being able to live with numbers as low as the equivalent of $500 a ton, which for us, if you convert it back into the lithium content of the tailings, benchmarks to approximately 30 to 50 US dollars. So it triangulates well with lithium coming out of Nigeria, for example.
Conference Operator
Operator
The second question from Rock Wolfman from JP Morgan is How should we think about your offtake strategy after the many offtakes is completed in a few months? Any discussions with partners from additional offtakes or pay payments agreements?
Ana Cabral
Co-Chair and CEO
Thank you very much. Doing a multi-year off-take agreement into the 2027 year. But typically for us, we've been achieving very successful commercial results by selling the material on maximum of what we call a quarterly contract. For instance, the previous quarter of the third quarter, we achieved the $1,485 realized price, which was very robust if you were to take into account the falling lithium price environment. and we have been over the piers when it comes to achieved realized prices. Why is that? As we're not hostages to an offtake, we don't price our products on formula, we use the market quote straight out of Shanghai metals market for concentrate, which essentially provides a more beneficial financial condition. We are considering to do a multi-year offtake into 2027, but it's not something necessarily we have to do. We can perfectly survive continuing to do what we always do with selling material on a one-year basis.
Conference Operator
Operator
I'm returning to our CEO, Ana Cabral, for her final remarks.
Ana Cabral
Co-Chair and CEO
Felipe and I and the entire Sigma team would like to thank you for your support throughout this quarter. We're very proud of how we came out of the third quarter into the fourth quarter. We came out stronger with tremendous visibility into our business, visibility such that the new governor of Minas Gerais has announced that he's going to take office from our region. So, in January, he's actually going to become governor in our region, in Vale do Jequitinhonha, which fills us with tremendous pride because we were able to shed the light in the transformational shared prosperity work we have been doing there for almost a decade. And that has culminated in Sigma becoming this key company in the Western and Eastern global supply chains. Delivering large-scale, low-cost, and traceability. Going forward, that decision by the newly elected government has fueled us with enthusiasm to full-on continue on our growth strategy. And again, starting bottom-up because the mind is what brings the most amount of jobs. And as a result, we plan to bring in another 25,000 people into the Prosperity Folder segment. So, working in an endeavor such as this is a partnership between the public powers, between society, and between the company. And as a good citizen company, we're really looking forward to contributing to lift the people of Vale do Jequitinhonha. And for that, I want to thank all of our stakeholders and our shareholders for being with us on this journey.
Conference Operator
Operator
The third quarter of 2026 conference call of Sigma Lithium has concluded. For further information please visit the company's website at www.sigmalithiumresources.com. You can disconnect now.