Venture Global, Inc. Q3 F2026 Earnings Call Transcript

AI Conference Call Analysis

Sign in or subscribe to read.
Debra
Conference Call Operator
Hello, everyone. Thank you for joining us and welcome to the Venture Global, Inc. Third Quarter 2026 Earnings Conference Call. After today's prepared remarks, we will host a question and answer session. If you would like to ask a question, please press star one to raise your hand. To withdraw your questions, press star one again. I will now hand the conference over to Ben Nolan, Senior Vice President of Investor Relations. Ben, please go ahead.
Ben Nolan
Senior Vice President of Investor Relations
Thank you, and good morning, everyone. Welcome to Venture Global, Inc.'s third quarter 2026 earnings call. I'm joined this morning by Mike Sabel, Venture Global's CEO, executive co-chairman and founder, Jack Thayer, our CFO, and other members of Venture Global's senior management team. Before I begin, I would like to remind all listeners that our remarks, including answers to your questions, may contain forward-looking statements, and actual results could differ materially from what is described in these statements. Thank you for joining us. I'll now turn the call over to Mike Sabel.
Mike Sabel
CEO, Executive Co-Chairman and Founder
Thank you, Ben. Good morning, everyone, and thank you for joining us today. We are pleased to share our third quarter 2026 results. I will begin the call with an overview of our key accomplishments in the quarter and an update on the business. I will then make some remarks on the LNG industry before turning the call over to Jock, who will provide a more detailed review of our financial results, as well as updated guidance for 2026. Following all prepared remarks, we'll open the call to Q&A. Beginning on page five, you can see several highlights for the quarter, including the company's largest ever quarterly EBITDA of $2.6 billion and significant growth year over year in volumes, revenue, income from operations, net income, and EBITDA. We are increasing our 2026 EBITDA guidance to $10 to $10.3 billion from $8.7 to $9.1 billion based on current market outlook for the remainder of the year. Jack will discuss these numbers in greater detail. We are also raising the low end of the expected cargo range by nine cargoes for 2026. Turning to page six, our operational and financial performance was very strong in the third quarter and the capstone of that operational execution occurred on October 31st as we commenced commercial operations at Plaquemines phase one. The team delivered COD within the original window period of our phase one contracts and has now loaded six SBA cargoes to customers since COD. Although this milestone occurred after the end of the third quarter, we wanted to highlight this significant achievement and recognize our team who successfully and efficiently completed complex and challenging rectification and commissioning work while sustaining our industry-leading safety record. Plaquemines Phase 1 commenced commercial operations just 53 months after FID, making it the fastest greenfield project of its size to progress from FID to COD and surpassing the record previously set by Calcasieu Pass. Commercial momentum continued in the third quarter as we executed 1.5 MTPA of new or increased LNG offtake agreements. We are pleased to add ConocoPhillips as a new customer with a 1 million ton per annum agreement, along with a new offtake agreement with China Gas for 0.5 MTPA. Additionally, just last week, one of our existing high-credit-quality customers increased their contracted volume by 0.5 MTPA. Demand for long-term contracts remains robust, and we expect to add more high-credit-quality 20-year SBAs before the end of this year. As we announced last month, we have entered into definitive reservation agreements with GE Vernova, GE Grid Solutions, and Baker Hughes for up to 16 power islands and associated grid equipment, enabling us to develop an island mode data center solution as a natural extension of our LNG business. Building upon our LNG and power expertise to create the first industrial AI utility offering, we believe our existing ability to deliver near-term power, turnkey in-house engineering, procurement, and construction, and manage significant volatility in power loads without relying on the public grid can provide a differentiated and actionable solution for compute providers. Moving to page 7. We have now contracted almost all of our 2026 cargoes with over 99% of the portfolio contracted from the 91% previously reported on our second quarter earnings call in August. The 124 cargoes produced in the third quarter were at the high end of our expected production range. We are raising the low end of the cargo range for the full year by nine cargoes. During the quarter, We are completing Phase 1 commissioning and rectification activities at Plaquemines, which did modestly impact production during the quarter. Moving into the fourth quarter, as anticipated, we have already seen an improvement in production. We will provide further 2027 production and pricing guidance on our fourth quarter call early next year, and we are maintaining our 2027 outlook. for 575 to 625 total cargoes next year, which includes 10 to 20 cargoes from CP2 during the third quarter, as we now expect production there to begin mid-year 2027. Taking a closer look at CP2 on page 8, construction continues to progress, and we are moving forward the target of first LNG to July 2027. That would be approximately 24 months after CP2 Phase 1 FID and meaningfully sooner than our previous industry record of 29 months from FID to first production. With each phase of our projects, our team has improved efficiency and speed to first production, which has consistently proven beneficial during this period of historically tight global LNG. For reference, Plaquemines produced 234 cargoes in its first year of operations. Building on lessons learned at that facility, we believe CP2 can ramp production even more quickly. On page 9, we discuss our bolt-on expansions at CP2 and Plaquemines. For the CP2 Phase 3, we are working with our legacy banks and expect to have financing in place soon, positioning us to make a final investment decision on the 10 MTPA expansion in early 2027. For the Plaquemines expansion, as previously disclosed, we are targeting FID of the first phase around mid-2027. To facilitate the expansion, we expect to build a new pipeline from North Louisiana called Cloud Connector to provide gas to support our Plaquemines LNG expansion, adjacent air utility site, and enable enhanced production from the original two phases of Plaquemines. On page 11, you will find our insights on the state of the LNG market. Thank you for joining us. Even with increased LNG imports, inventory builds have lagged typical levels as EU gas storage is at its lowest early November level since 2013, pointing to stronger underlying demand growth. Europe has been using gas as a balancing fuel to offset variability from other sources of electricity. Severe droughts led to lower river levels and limited the cooling capacity of nuclear power plants, Contributing to a 7% year-over-year decline in electricity generation from EU nuclear facilities. Looking ahead to the winter, wind power represents approximately 20% of Europe's electricity generation and forecasts for the next several months call for volatile wind conditions with periods of low wind alternating with high output storm periods. This outlook underpins potentially significant natural gas demand during the heating season. In Asia, Many markets looking to manage geopolitical risk have increased coal consumption as an alternative to buying spot LNG. The switching has pressured coal inventories and contributed to sharply higher coal prices. As highlighted by recent Indonesian coal force majeure events, coal is providing less relief. As a result, LNG markets in Asia and throughout the world are becoming increasingly inelastic. These examples illustrate several drivers of near-term demand. If LNG volumes coming from the Middle East remain limited, we expect LNG prices to remain volatile this winter and potentially move higher from currently elevated levels. Notably, Blackman's production this past year offset roughly one third of the global supply impact stemming from disruptions in the Middle East, helping stabilize prices for consumers globally during this period of volatility. As CP2 targets starting production in July, Venture Global's LNG projects will continue to offset potential broader supply disruptions, support global demand, and act as a reliable, stabilizing force in the market. While LNG prices remain high, energy buyers have taken an all-of-the-above approach encompassing fuel switching, demand management, and utilization of storage. We have not seen permanent demand destruction or a shift away from LNG as a strategically significant energy feedstock. Nothing illustrates this more clearly than continued demand for new long-term contracts and the robust growth of new LNG import project development activity. As shown on page 12, we count more than 30 incremental projects that have been announced and are in various stages of development since the beginning of the year. While not all of these projects may materialize, demand for power and L&G is unquestionably growing. At least in the case of venture global, I think it is fair to characterize demand for long-term contracts as stronger than it has ever been, particularly from Asian buyers. We believe this strong contract appetite reflects continued growth in global energy consumption throughout the world and the value proposition of buying long-term fixed margin Henry Hub-linked L&G at prices that make electricity affordable and available in all market cycles. Turning to page 14, as announced earlier in October, we entered a power frame agreement with GE Vernova and Baker Hughes for up to 16 power island units. Each island has gas turbines, heat recovery steam generators, and steam turbine generators, which gives us about 720 megawatts of combined cycle capacity per island. We have also entered A second frame agreement with GE Grid Solutions for associated gas-insulated switch systems, power transformer, and equipment necessary to manage the load volatility inherent to compute. These new frame agreements provide for incremental power supply optionality above and beyond the remaining equipment available under our long-term Baker Hughes Master Agreement, which governs the supply of key power and liquefaction equipment that has successfully underpinned our growth for over a decade. Under these contracts, we plan to order one power plant before the end of this year and a second one early next year. As we secure off-take contracts with investment-grade customers, we have the option to build out further power and data center infrastructure. We intend to develop this business with the same disciplined approach we have always taken. This means advancing incremental capacity alongside investment-grade customer commitments and maintaining a clear focus on attractive risk-adjusted returns. We expect the first 250 megawatts to come online in late 28, are targeting 5 gigawatts by the end of 2031, and have the potential to reach 10 gigawatts by 2034 across our two sites in Cameron Parish and Blackman's Parish. On page 15, if you look at the AI ecosystem on the left, there are five necessary contributing layers of energy, infrastructure, chips, models, and applications. Our AI utility offering is focused on two of the most difficult layers to deliver, infrastructure and energy. We believe our ability to provide both on an integrated basis can offer a differentiated turnkey solution at scale. We view this as additive to our current LNG business and as a natural extension of what we have done since Venture Global's founding, successfully and quickly building and operating power equipment and infrastructure at a massive scale. We already have approximately 15,000 acres of land and access to roughly 13 BCF per day of pipeline capacity, making us one of the largest gas buyers in the country. We have over four gigawatts of island mode power currently operating or in development on our own private grid and a thousand person in-house execution and EPC team. We've built ports and fabrication yards, developed supply chain and quality control teams and executed thousands of scopes across $70 billion of industrial assets. Compared with our LNG projects, power for compute is a relatively simpler and narrower scope. Data centers place heightened demand on power systems as their load is not steady. Power demand can rise or fall sharply, which creates a real reliability challenge for most power providers, necessitating utility-grade connectivity to manage this volatility. Venture Global's design is built to meet this volatility challenge as our industrial energy grid already reliably absorbs significant load swings in island mode in a liquefaction facility operations today. For potential customers, that adds up to a dramatically better and more reliable product, one that offers speed and scale. We believe initial compute capacity could be available in late 28, early 29, and could scale to five gigawatts by the end of 2031. Also, our island mode solution solves for the challenge of connecting to the public power and water grid bypassing interconnectivity hurdles. Venture Global's AI utility would have no added cost to local consumers. Our solution is designed for reliability with a target of greater than 99.9% uptime supported by multiple layers of redundancy. We can achieve all this with no impact on the local community as we don't rely on the local electric grids or water utilities. Further, we are well capitalized and do not expect to need any outside equity to fund our current build plans. Operationally, this is a natural fit with our existing construction program, which should be ramping down from large-scale greenfield operations at CP2 and focused on the smaller brownfield scopes at CP2 and Blockman's as construction begins to support our AI utility offering. Customer interest to date supports our view that this is a low-risk, high-value, differentiated market offering. We are working hard to secure commercial agreements and are excited about the opportunity to deploy a unique combination of experience, skills, infrastructure, equipment and capital in this rapidly growing market that needs partners capable of delivering this one-of-one turnkey offering. I will now turn the call over to our CFO, Jack Thayer, who will review the quarterly performance, provide an overview of our project performance and discuss our updated financial guidance.
Jack Thayer
Chief Financial Officer
Thank you, Mike, and good morning to those of you on the line. I'll be starting on slide 17. I'll be referring to the Venture Global, Inc. Form 10-Q for the quarter ended September 30th, 2026. The 10-Q is available on our website and some of the key results are summarized on page 17 of the presentation. During this call, I will highlight results we believe are salient to this audience and I encourage you to review the entirety of our financial statements in detail. Beginning with revenue, our top line was $4.8 billion for the third quarter of 2026, a $1.4 billion Thank you for joining us. with $10.16 per MMBTU earned in Q3 2026 compared with $8.92 per MMBTU earned in Q3 2025. Our income from operations was $2.3 billion in the third quarter of 2026, a $1 billion or 74% increase from $1.3 billion in the third quarter of 2025. G&A expenses increased slightly year-over-year, attributable to higher headcount. Our net income attributable to common stockholders, which we refer to as net income was $2.5 billion for the third quarter of 2026, a $2.1 billion or 493% increase from $429 million in Q3 2025. Again, the most impactful driver of higher net income was increased volume and prices. But in the quarter, we also recognized a $1.4 billion non-cash gain on interest rate swaps, which was slightly offset by higher income tax expense. Shifting to consolidated adjusted EBITDA, we earned $2.6 billion during the third quarter of 2026, a $1.1 billion or 69% increase from $1.5 billion in Q3 2025. Thank you for joining us. including to fund early project costs at the CP2 and Plaquemines-Bolton expansions. Through September, we also utilized project distributions to repay $1.8 billion of CP2 Phase I equity bridge drawn capacity. We expect to repay the remaining $0.2 billion balance of the $3 billion facility in Q4 2026. Bolstering our liquidity, we also finished the quarter with $5.1 billion of cash and restricted cash. As you can see on page 18, we are providing a consolidated adjusted EBITDA guidance range of $10 billion to $10.3 billion for 2026, which is up from $8.7 billion to $9.1 billion when we reported in August. This range contemplates a current market liquefaction fee of $21 to $22 per MMBTU for cargoes remaining to be sold in 2026. On average, if the fixed liquefaction fees over the remainder of 2026 increase or decrease by $1 per MMBTU, we expect our consolidated adjusted EBITDA range to adjust accordingly by $20 to $30 million. Reflecting an LNG portfolio where 99% of our expected 2026 cargoes are now contracted. We plan on providing 2027 EBITDA guidance on our next quarterly earnings call. It is worth reminding you all that there will be an impact to contracted Phase 1 margins from the start of our long-term contracts at Platkins. We also expect continued basis impact on the gas used at that facility and there are likely to be some costs associated with ramping up the startup of CP2 and the development of our AI utility business. Given the positive market backdrop and our progress on CP2 construction, we're optimistic about another year of strong results. I'll now turn the call back over to Mike. Thank you, Jack. At this point, we'd like to open up the call for Q&A.
Debra
Conference Call Operator
We will now begin our question and answer session. Please limit yourself to one question and one follow-up. If you would like to ask a question, please press star 1 to raise your hand. To withdraw your question, press star 1 again. We ask that you pick up your handset when asking a question to allow for optimum sound quality. If you are muted locally, please remember to unmute your device. Please stand by while we compile the Q&A roster. Your first question is from the line of Praneeth Satish of Wells Fargo. Your line is open. Please go ahead.
Praneeth Satish
Analyst, Wells Fargo
Good morning. Thanks. Good morning. Maybe can you walk us through how quickly CP2 ramps after first LNG? I guess looking at your full year 2027 guidance, it implies a big step up in the fourth quarter of 27. Just trying to figure out how much of that is seasonality versus the CP1 debottleneck versus the CP2 ramp. So just anything on the slope of production at CP2 would be helpful.
Mike Sabel
CEO, Executive Co-Chairman and Founder
Sure. The best guide is to look at the ramp up for Plaquemines, which in the script we just read here, we reminded that we produced 234 cargos in the first 12 months for Plaquemines. We studied, as we do very carefully, the opportunities to improve on that. And we think there are opportunities for improving the ramp up for CPT relative to Plaquemines. but that ramp up for Plaquemines we view as a really good baseline opportunity. So given the massive scale of CP2, we think the opportunity there is significant.
Jack Thayer
Chief Financial Officer
Mike, we also will see some improvement at Calcasieu Pass in the fourth quarter as we benefit from the bottlenecking that we're doing there during the summer. During the summer, yeah.
Praneeth Satish
Analyst, Wells Fargo
That's helpful. And maybe switching gears to the power side. So obviously, you know, big opportunity for you guys. But can you just help us understand how are you thinking about financing for the first set of power islands? And really, it's on the debt side, I guess we've seen financing costs widen for some of the data center projects where they don't yet have customers fully committed. And so Do you think that is a risk to the pace of your build-out and maybe points to something of a more measured build-out as you wait on customers? Or do you think the economics are still strong even with an increase in financing costs?
Mike Sabel
CEO, Executive Co-Chairman and Founder
The margins are still fantastic, even with higher financing costs, assuming that we're able to contract on a triple net lease basis in line with where others are contracting in the market. When you look at the timing of the first compute that we think is possible to bring on, matching with the delivery schedules of the equipment, is late 28, early 29. And so it's out a couple of years. And we're looking to build in 250 megawatt compute building increments. and then ramping up after over the course of 29 and into 2030. So there's a reasonably gentle ramp up in what that cost would look like that spreads into really mostly into 29 and 2030, which matches up nicely with the big ramp up in cash generation by the LNG business. We think that timing is going to turn out to be well-suited for the build-up in cash that we expect as we more than double the production capacity, bringing online CP2 and the first bolt-on for CP2 and the first bolt-on of Blackman's. The first power plants... We'll begin to place some orders for those as we've guided to shortly. But the payments for the power plants are spread out over a few years as those get built. We believe we purchased some at a great price. Thank you for joining us. We think we have really nice optionality on how we take advantage of the value from those power plants. Again, we know the market for power plants that deliver in the next few years is extremely high. extremely attractive just given the demand of hyperscalers and utilities, not just in the U.S., but globally chasing power generation equipment.
Praneeth Satish
Analyst, Wells Fargo
Got it. Very helpful. Thank you.
Debra
Conference Call Operator
The next question is from the line of John McKay of Goldman Sachs. Your line is open. Please go ahead.
Mike Sabel
CEO, Executive Co-Chairman and Founder
Good morning, John.
John McKay
Analyst, Goldman Sachs
Hey, good morning, Mike and team. Thanks for the time. Maybe picking up on that last question a little bit, but just thinking about the remaining LNG build out, can you just remind us the capital you need to fund the remaining 85 MTPA and then any kind of guidance you can give us on kind of the cash generation you'd expect to make over that period? Just trying to think of, you know, completing the LNG build out as you kind of make this shift into the data center side.
Mike Sabel
CEO, Executive Co-Chairman and Founder
Sure. So the next financing is going to be for the bolt-on for CP2 Phase 3, which is adding 12 LNG trains and approximately 10 million tons of additional production capacity. The financings are going to look generally similar to what we've done, which will be a combination of of bank construction debt at the project level and other debt facilities at the project level. A little bit of contributed cash equity from the parent. We do not expect to raise any parent level equity or debt like has been the case for the previous transactions. The bolt-on for Plaquemines we're guiding to the first half of next year. The first phase of that is adding eight trains. So it's a little bit fewer trains in the next phase for the bolt-on at Plaquemines. And that number of trains matches up nicely with how it integrates with the with the balancing plan for phases one and two at Blockman's. And so that financing sequence we expect to have done by the middle of next year. before we begin to shift over to the financings for the build out of the AI compute opportunity. Again, provided we're signing customer contracts to match up with that growth. The cumulative EBITDA from today for 27, 28, 29 is significant. And my view is that it's going to, in aggregate, be in excess of $30 billion, depending on your price assumption on the sale of cargoes in the future. And so we have significant retained earnings accumulation that supports the LNG buildup, plus Any incremental equity to support financing for contracted data center buildings and also amortization of debt and a nice cash cushion. Today, if you took note from a few minutes ago, Jack showed that we have today $5.3 billion of cash. And so while we've been growing our business, significantly in the last year, adding $18 billion of assets and increase in production capacity. We've also been able to manage the cash balance attractively.
John McKay
Analyst, Goldman Sachs
Thanks, Mike. Appreciate that. And maybe just thinking about the LNG build-out, but pulling the macro in a little bit, can you just share some of your thoughts on what the contracting environment looks like right now? We've seen have a new buyer come into the U.S. contract market. That's a little different from what we've seen before. So any kind of thoughts you can share on the general contracting environment and what your appetite to sign new long-term deals is right now? Thanks.
Mike Sabel
CEO, Executive Co-Chairman and Founder
Yeah, no, it's an extremely attractive 20-year market or active 20-year market for us right now. Probably as good as we've seen since the beginning. And we're... expecting to sign more 20-year deals this year and next year. The market has shifted to, for the moment at least, to more buyers coming from Asia than Europe, which is a pivot from the last couple of years. One that we expected but has arrived now. We feel good that we'll be able to layer into the portfolio the additional 20-year SPAs that we want. And we also think that we'll see increasing appetite for midterm deals as well, five-year to 10-year deals. And so we'll probably look to add some of those next year as well.
John McKay
Analyst, Goldman Sachs
That's clear. Appreciate the time. Thank you.
Debra
Conference Call Operator
The next question is from the line of Spiro Dunas of Citi. Your line is open. Please go ahead. Good morning.
Spiro Dounis
Analyst, Citi
Thanks, Debra. Hey, good morning, Mike. I want to just follow up actually on that last question with respect to contracting activity. Mike, you maybe level set us on what's still needed to commercialize the next expansions at Cal State Pass and Plaquemines. The slides point to about 30 MTPA still available. So I wanted to get your sense on how you're thinking about what that looks like post-FID and how much you'd be willing to contract out.
Mike Sabel
CEO, Executive Co-Chairman and Founder
We're in a good position to finance today what we need where we already have what we need to do the FID for the CP2 bolt-on. And it's a brownfield expansion. We expect to We expect and plan to have more this year some of which will be assigned to that bolt-on expansion and others that will shift over to the Plaquemines bolt-on. For the Plaquemines bolt-on, we could finance that one ahead of additional 20-year deals, but given the cadence of our activity, We expect to have two or three more or more to support the timing of the FID for Blackman's. We expect to have all that contracted on a multi-year basis. A five to 20 year basis is probably the likely range. We have A heavily weighted portfolio today, heavily weighted to 20-year deals. So our overall portfolio length is really long. And we'd like to add more midterm deals so we can add more price and still end up with a very long term. So of that remaining 30 million tons out of the... I can't remember what page number that has been, but out of... The 85 we have coming online in the next few years. Those will be done on a blend of five-year deals, 10-year deals, 20-year deals, two-year deals. We have a few years to blend those contracts in. We're not going to rush out and Do them all in the next few months and quarters. We'll spread them out to kind of a blend of term. If we did half of that on a midterm basis, we're still going to have a contract length that's 13, 14, 15 years in term, which is still a long life portfolio.
Spiro Dounis
Analyst, Citi
Got it. Appreciate the color on that. Switching gears back over to the power side and just to focus on the power returns, I guess, and not sure how much you could say right now, but can you talk about the relative returns on power and how that compares to LNG and where some of those trade-offs might be? And similarly, is there an easy way to think about the unit economics and CapEx on each of these 250 megawatt units?
Mike Sabel
CEO, Executive Co-Chairman and Founder
So the returns, if we just did, Power and didn't also build the data centers might be a little bit higher, but we wouldn't be deploying that much capital. The returns on a combined basis of power plus data center buildings is higher than the returns on the LNG side, provided that we're contracting in line with where others are contracting in the market. It's not a neither or, though. We're going to continue building the LNG and we're going to build out our grids in order to support data center demand. So we think it's a very attractive addition, again, if we're able to execute the triple net lease contracts. And we think that it will provide a really nice kind of a blend of contracts that are also long-term but don't have the same commodity price exposure. And so as we layer those contracts in, it will blend out that volatility and we think be very attractive for shareholders.
Spiro Dounis
Analyst, Citi
Great. I'll leave it there.
Debra
Conference Call Operator
Thank you. Thank you. The next question is from the line of Manav Gupta of UBS. Your line is open. Please go ahead.
Manav Gupta
Analyst, UBS
Morning. Morning. Hey, Mike and Tim, I'm trying to understand as I look at the slide 24, what is, in your opinion, the optimal mix of contracted versus uncontracted capacity as you are trying to enter a new year? So let's say, where would you like to be somewhere in December 2027 and then again December 2028? As you enter those years, what would be the right mix of contracted versus uncontracted capacity?
Mike Sabel
CEO, Executive Co-Chairman and Founder
So, you know, not all the volume, obviously, in these charts exists today. It's it's some of it's a lot of it's in construction with CP2 and in development with the bolt ons. And so we don't have to do it all. and so we have time to blend in the contracts we have over 50 million tons of contracts today almost all on a 20 year basis and so we have room in our portfolio to capture more price by doing shorter than 20 year deals and so we expect The vast majority of this to all be contracted in the next couple of years. But we'd like to do more midterm deals to blend down the 20-year term and hopefully achieve a higher price in the market today. As I'm sure you know, as you go shorter in contracted term, the prices are higher. And we have room to add... Add a decent amount of midterm deals and still have a very long portfolio of contract term. It's difficult to give an exact blend today of where we're going to be a year from now and two years from now because we don't know the market price to be able to do it. And obviously, we're always reacting to the market price. We think that The fundamentals that are true in most commodity markets will continue to be the case here, which is replacement cost drives the market price over time. And we think that construction costs are going to continue to inflate. We think that interest rates are more likely to stay the same or go higher than go lower in the next couple of years. and that signals higher replacement costs. And so we think over a multi-year period supports increasing price opportunity that we want to blend into over time.
Manav Gupta
Analyst, UBS
Perfect, sir. My quick follow-up is on the power side. A lot of companies are trying this. I'm trying to understand from Venture Global's perspective What are the strategic advantages that your company has? Why would you feel that the AI data centers would like to partner with you? What advantages can you bring to the table versus some of the multiple solutions that are out there? Thank you.
Mike Sabel
CEO, Executive Co-Chairman and Founder
Sure. Well, one of the big challenges that exists In the compute market today is really the scarcity of electricity being available to power the buildings in the compute. And a big part of that is the ability or the difficulty in connecting to utility grids as they have in the past. And it's political and regulatory. and the other component of it is the ability to manage the scale and variability of the compute loads as the compute utilization goes up and down sometimes in milliseconds. So the market and response as we've all seen over this year is to start to build power plants separate from the utility grids and contribute that power to the grids The data centers largely remain connected to the grids in parallel to connecting with the incremental power, which means that they continue to use throughput capacity in the transmission lines and the grids of the utilities, which we think will remain to be a large impediment to the growth of the market. In our case, we have developed over many years and built and now operate multi-gigawatt grids that manage the variable load of our LNG facilities and have demonstrated to be very reliable in managing that variability and providing high quality power for, in our case, LNG production. For us, we can expand our existing grids to provide significantly increased power generation combined with data center buildings to support the compute demand all in island mode. So we're not connecting and reliant on the utility grids. We have no impact on the community's grids or available power generation or prices, and we're not reliant on the water utilities either. So in an environment where We think that's one of the primary challenges to growth we think we solve entirely. We also have built out, as you know, our own execution team that engineers, procures, builds, commissions, and operates these complex electrical grids. And so we think it's including gas supply. Thank you so much. Thank you.
Debra
Conference Call Operator
The next question is from the line of Jean Ann Salisbury of Bank of America. Your line is open. Please go ahead. Good morning.
Jean Ann Salisbury
Analyst, Bank of America
Hi, good morning. I know it's early, but do the midterm election results affect how you see the power frame opportunity and the geographic areas that you're targeting, which from slide 14 looks like it's basically all Louisiana? And could you actually see Louisiana potentially gain market share and data centers from this?
Mike Sabel
CEO, Executive Co-Chairman and Founder
Yes, we think Louisiana has a significant advantage in the market. For the moment, it seems like they might be the only store open on Sunday here for data centers. And combined with our offering, which is island mode, we think that it creates a significant scarcity value at scale. for how we can execute this. It appears that the other states are going to take a while to kind of decide what they want the new rules to be for expanding powered data centers and compute. And Louisiana, particularly with what we've already executed and how large an investor we are today in Louisiana, is open for business. And we think Louisiana has a great opportunity to significantly add to their existing gas businesses in the state and become a major supplier of compute in the United States.
Jean Ann Salisbury
Analyst, Bank of America
That makes sense. Thank you. And then a follow-up on slide 14. Thank you for the split of your outlook for the power frame business into Cameron Parish versus Plaquemine Parish. Currently, you know, there's some pretty severe gas constraints going into Plaquemine Parish, which I guess would just get worse if you added power and Plaquemine both times. Do you think that you need to see pipelines come in to fix those constraints before you'll be able to really get customers to sign up there?
Jack Thayer
Chief Financial Officer
Jeanann, this is Jack. So importantly, there are two pipes that are coming online in 2028 that will address some of that constraint that we've been seeing in our basis projections. But I would add that the cloud connector pipe that Mike announced in his prepared remarks and many more. but also the development of the Western Haynesville and the Shelby Trough and that gas coming over as well. I'd also note that production within Haynesville has been incredibly high volumes in what has been a low price environment. That's always viewed as the most price sensitive market. but we see developers and upstream producers earning attractive returns in a low price environment and we expect them to continue to maintain their production and in fact grow their production as new demand comes online.
Jean Ann Salisbury
Analyst, Bank of America
That makes sense. Thank you.
Jack Thayer
Chief Financial Officer
Thank you.
Debra
Conference Call Operator
The next question is from the line of Chris Robertson of Deutsche Bank. Your line is open. Please go ahead.
Chris Robertson
Analyst, Deutsche Bank
Good morning. Thank you, operator. Good morning, Mike. Just first question on the Power Island AI side. I think the power offering is pretty clear, but can you talk more about the additional infrastructure offering that you guys will be providing, including some buildings and other design elements? And can you talk about was this engineering work already done in-house or are you still developing plans around that?
Mike Sabel
CEO, Executive Co-Chairman and Founder
The infrastructure offering is really just the data center buildings in combination with the integrated power. That's the bulk of it. Obviously, it includes cooling systems as well. There's an envelope inside the building where we hand off to the customers of the compute. Again, when we sign these, we're assigning triple net leases to on the power buildings. And so the envelope inside is going to depend on who the customers end up being. And we're building, our target is to build incrementally 250 megawatt compute buildings. And so we have room to have multiple customers between buildings, if that's how it turns out. and so it's possible there would be different designs within the buildings. We manage, as we build on the LNG infrastructure side, teams of multiple subcontractors and It'll be similar for the data center buildings where we tap into specialist contracting firms that provide different aspects of the construction and engineering for specialized systems. And that's exactly the same way we do it at a larger scale on the LNG side. but the power systems we're very familiar with which are the gas insulated switch buildings, the e-houses, the transformers and the power generation itself is nearly identical. We'll be adding layers of batteries and air derivatives but we in our LNG facilities have networks of battery systems and air derivatives as well designed to manage variable load. So it's very, very similar.
Chris Robertson
Analyst, Deutsche Bank
That's clear. Maybe one for Jack or Mike, you could probably answer this as well. But, you know, 2027 will be the first full year of commercial operation at both CP as well as Plaquemines in terms of the base production. So can you talk about maybe expectations around what percentage of full year EBITDA or revenues for 2027 will be derived from the from the contract agreements versus any spot or commissioning volumes?
Jack Thayer
Chief Financial Officer
Chris, in terms of 2027, the split will be given that Phase 2 will come online the middle of next year for Plaquemines. in COD format, and those contracts will start. We'd still anticipate that the prevailing market prices will be the major driver of our earnings in EBITDA during 2027. And that forward curve looks attractive at current prices. And as we play through the winter here, We anticipate that bow waving into 27 as Europe in particular addresses a storage shortfall.
Mike Sabel
CEO, Executive Co-Chairman and Founder
I would pause and think about the data we talked about earlier on the call, which is the ramp up for the first 12 months of Plaquemines was 234 cargos. And How hard we've worked kind of looking for opportunities to make improvements in that ramp up schedule. And obviously the guidance we just gave to vectoring towards a July 1st LNG date. And so it's a pretty significant move moving the... This is the first LNG date from the winter into the summer there, to the middle of the year.
Chris Robertson
Analyst, Deutsche Bank
Great. Thank you, Mike. I'll turn it over. Thank you.
Debra
Conference Call Operator
The next question is from the line of Elvira Escotto of RBC Capital Markets. Your line is open. Please go ahead.
Elvira Scotto
Analyst, RBC Capital Markets
Good morning. Thanks for taking my question. So you talked a little bit about this already, but with the new AI data center initiative, you know, obviously, given your expertise in power, this seems to make a lot of sense. But how should we think about, you know, capital allocation? How are you deploying human and other resources to LNG versus power? and what are the latest thoughts on that sort of getting to investment grade in light of this new business and then just capital return to shareholders?
Mike Sabel
CEO, Executive Co-Chairman and Founder
So, wow, those are a lot of great questions. So first of all, in terms of resource timing, we're actually getting ready to come off peak at CP2 already, which when you think about our guidance on when we're going to start Get to first LNG would be expected. In the bolt-on at CP2, a lot of that activity happens at the factory. The incremental 12 LNG trains, the first bolt-on train is going to be the 91st train that we commission and turn on. That's being built over in Italy and they'll roll over and slide on to Foundations, the power plant we ordered a long time ago. It's a similar power plant. We have very little pipe rock for this phase three. So when you compare and then the Plaquemines bolt on, it looks like it's gonna just trail by about six months. And that's eight trains in the first phase of that. So it's a very manageable execution that kind of just staples on to the remaining activity. And the big ramp up for the data centers, again, if and when we sign off-date contracts happens really more, you know, some in 28, but really more 29 and 30. and so it gives us a great scope to apply this amazing team, this giant team that we built that has, we think, an amazing set of skills and capacity. And so from an execution allocation perspective, this blends in really nicely with kind of the tapering of the most intense LNG construction and commissioning activity. That lag in timing also plays very nicely into the deployment of capital. Again, if we're able to sign triple net leases, that capital requirement pushes out to 29 and 30. The 250 megawatt buildings The rest of the industry builds those today in the $5, $6, $7 billion range, not including the chips. We're going to do this if we're able to do this with investment Craig counterparties. and so the incremental capital requirements for those are manageable relative to our size, particularly out in 28, 29, 30 as we're significantly ramping up production and cash flows. We load, give or take, 43 cargoes a month now and 24 months from now that'll and so we have a very significant build up of cash and so we think it's a really nice way to deploy a lot of extra capital that we think actually will improve our path to investment grade as we increase contracted long-term sales of the triple net leases and hopefully significantly increase our cash generation and earnings. But we have in coming years cumulatively tens of billions of dollars of cash generation. And so we have plenty of room to manage to investment grade at project levels and at the parent level. Pay Down Debt, and Buy Back Stock if we think the stock price remains attractive and too low from our perspective.
Elvira Scotto
Analyst, RBC Capital Markets
Great, thank you. And then just in terms of, I mean, I know you announced this recently, but presumably you've been working on this for a while, but can you give us a sense of... Just the appetite from hyperscalers. Have you already started having discussions with some counterparties? And then what's the sort of typical lead time from customer commitment to revenue commencement?
Mike Sabel
CEO, Executive Co-Chairman and Founder
So we've been working on this for seven to eight months now and only announced it recently as we executed, I think three weeks ago now, the expansion of the frame agreement with GE. and we really needed to have that in place to have the most serious conversations with potential customers because the scarcity in the market has been the ability to actually acquire the near-term power generation equipment and the switchgear and transformers and so that needs to be in place for not just us but any counterparty to close out deals with customers on specific schedules. On the prediction and timing, we've never signed a triple net lease before so we're not experts on predicting the timing of those. We've done give or take $140 billion of long-term contracts with L&G customers. We're able to give you better predictions on that side. We want to remain very conservative on comments on timing. We know we can execute it. We now know we've secured the supply chain to match up with our execution capacity. We have room to do it. We've permitted for 10 years. Similar infrastructure in our locations. We're in a great state to do it. We have the capital capacity to do it, but we haven't signed the deals yet. And so that's what we're working on.
Elvira Scotto
Analyst, RBC Capital Markets
Great. Thank you very much.
Debra
Conference Call Operator
Thank you. We've reached the end of the Q&A session. I will now turn the call back to Mike Sabel, CEO, Executive Co-Chairman and Founder for closing remarks.
Mike Sabel
CEO, Executive Co-Chairman and Founder
Great. Thanks for everyone's time this morning. We are extremely pleased with the progress that we made this quarter. We're hard at work safely executing our current construction and growth projects and Look forward to speaking to many of you in coming days and weeks and are excited for our next quarterly call already. So thanks everybody. Have a great day. This concludes today's call.
Debra
Conference Call Operator
Thank you for attending.
Mike Sabel
CEO, Executive Co-Chairman and Founder
You may now disconnect.